Google Cloud europe-west4-a: Grid Transient, DRUPS Failure and Chiller Shutdown
Summary
On 15 July 2026 a 3 ms grid transient tripped both utility feeds at the facility hosting Google Cloud zone europe-west4-a. The side A rotary UPS failed, one row lost power on transfer, and the chiller controller dropped out so the pumps stopped while the backup cooling was out for construction. The hall reached 44°C and equipment was shut down; customer disruption lasted 14 hours 55 minutes.
- Users affected
- 24 VMware Engine private clouds of 20 customers, 9 Bare Metal Solution customers, and NetApp Volumes customers on all 6 clusters in europe-west4-a.
- Duration
- 14h 55m — Customer disruption from 16:39 PDT 15 Jul → 07:34 PDT 16 Jul (14 h 55 min)
- Financial
- Not disclosed
- Scope
- Single data hall: power loss to one row and hall-wide thermal shutdown
- Site
- Facility hosting zone europe-west4-a · Site not named, Netherlands, europe-west4-a
- Services down
- Google Cloud VMware Engine, Bare Metal Solution, Google Cloud NetApp Volumes
How the defences failed
One data hall serving three specialised products; 33 named customers plus NetApp Volumes users. Duration (6): 14 h 55 min, inside the 12–24 h band. No cost is disclosed, so financial is judged moderate.
All 9 impact metrics
| Utility voltage transient | 3 ms, on both feeds A and B |
| Peak data hall temperature | 44°C at 18:29 PDT |
| Power event to 44°C | 2 hours 5 minutes (16:24 → 18:29 PDT) |
| Cooling lost | about 4 hours 41 minutes (16:24 → 21:05 PDT) |
| Total customer disruption | 14 hours 55 minutes (16:39 15 Jul → 07:34 16 Jul PDT) |
| VMware Engine customers affected | 24 private clouds of 20 customers |
| Bare Metal Solution customers affected | 9 customers |
| NetApp clusters shut down | all 6 |
| Rows on feed A that had to transfer | 3; Rows 1 and 2 transferred, Row 3 lost power |
Sequence of events
- TRIGGER An electrical fault occurred on the utility grid upstream of the data center: a 3 ms voltage transient hits both utility feeds A and B, both utility breakers trip and the site transfers to its diesel rotary UPS (DRUPS).Utility / grid operator
- TRIGGER Side B transfers to DRUPS without interruption. The DRUPS for side A fails to take over the load because of electrical component failures.
- TRIGGER The chiller controller drops offline during the transient, so the chilled-water distribution pumps stop and cannot restart and chiller system A shuts down. The redundant cooling source is out of service because of known ongoing construction work.
- DETECTION Google engineers were alerted to the infrastructure power loss by automated monitoring; the VMware Engine power-monitoring alert fires.Operations lead
- DETECTION NetApp's remote facility monitoring alerts on high temperature and network switch failure.
- CASCADE The three rows on feed A transfer to feed B. Rows 1 and 2 transfer; Row 3 fails to transfer because an overload protection breaker trips, and loses both feeds.
- IMPACT Customer disruption begins in europe-west4-a for VMware Engine, Bare Metal Solution and NetApp Volumes.
- IMPACT Network switch temperature alerts above 60°C trigger as the hall heats without chilled-water flow.
- CASCADE All 6 NetApp clusters shut down automatically because of high temperature.
- IMPACT Data hall temperatures reach 44°C and cross the safe machine operating threshold.
- CASCADE Four NetApp SAN storage nodes serving Bare Metal Solution fail and shut down from overheating; the first customer server shutdown follows.
- MITIGATION Google engineers start machine shutdown procedures for the reachable devices as part of the cooling emergency shutdown; all reachable server and network devices are off by 19:55.Service recovery lead
- MITIGATION The facility team switched the distribution pumps from auto to hand mode to restore circulation and cooling, and deployed an interim portable UPS to keep the chiller controllers powered.Mechanical / cooling engineer
- RECOVERY The cooling system is fully recovered and data hall temperatures return to the normal operating range.
- RECOVERY Notification about cooling recovery sent by provider at 21:24, followed by the power recovery notice at 21:46.Vendor / upstream provider
- RECOVERY With the fault isolated, teams reset the tripped breakers to re-energise Row 3; two remote power panels needed manual verification, and a swing DRUPS unit was aligned to restore redundancy on feed A.Authorised electrical person
- RECOVERY Onsite technician arrived to recover the console servers; console recovery completes at 23:10.First responder
- RECOVERY All 6 NetApp clusters and their customers are recovered and validated.
- RECOVERY VMware Engine incident mitigated: all customer private clouds are healthy.
- RESTORED End of the customer disruption window across the affected products in europe-west4-a.
- RESTORED Bare Metal Solution mitigated: every impacted customer server rebooted and confirmed healthy.
Response by role
What each role did
Roles the sequence of events shows acting; every entry quotes its source line. Select a time to jump to it.
Role by role
Recorded actions / playbook actions per role. A role with 0 recorded actions does not appear in the sources.
The grid operator upstream of the facility, not named — External owner of the supply: switching at the substation, load shedding, restoration.
On the record
- Grid fault upstream caused the 3 ms transient on both feeds
An electrical fault occurred on the utility grid upstream of the data center
Playbook analyst guidance by failure mode, not a record of what happened
The data center provider operating the facility, not named — Third party whose product, service or network sits in the failure path.
On the record
Playbook analyst guidance by failure mode, not a record of what happened
The facility team that reset breakers and aligned a swing DRUPS, not named — Switching, isolation and lock-out of power sources, and safe re-energisation.
On the record
- Re-energised Row 3 after isolating the fault and aligned a swing DRUPS
teams reset the tripped breakers to re-energise Row 3
Playbook analyst guidance by failure mode, not a record of what happened
The facility team that put the pumps in hand mode, not named — Chillers, CRAH/CRAC, pumps, cooling towers and the thermal envelope of the white space.
On the record
- Restored chilled-water circulation by running the pumps in hand mode
switched the distribution pumps from auto to hand mode
Playbook analyst guidance by failure mode, not a record of what happened
The onsite technician who recovered the console servers — Meets the first alarm: on-shift technician or security in a facility, on-call engineer in a service.
On the record
Playbook analyst guidance by failure mode, not a record of what happened
No incident commander is named in the record — Owns every decision until formally relieved: site duty manager on scene, or the declared IC of a service incident.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
- FM-04Declare a thermal emergency early and start shutdown before the envelope is crossedNIMS / ICSLesson #5
Google engineers alerted by automated monitoring — Technical lead who diagnoses and drives the fix; the subject-matter expert at the keyboard or the switchboard.
On the record
- Alerted by monitoring six minutes after the transient
Google engineers were alerted to the infrastructure power loss
Playbook analyst guidance by failure mode, not a record of what happened
Google and NetApp teams shutting down and restoring equipment — Restores customer service: failover, workload moves, capacity, backlog drain.
On the record
- Ran the cooling emergency shutdown for reachable devices
start machine shutdown procedures for the reachable devices
Playbook analyst guidance by failure mode, not a record of what happened
- FM-02Bring Row 3 workloads back in order and verify redundancy on both feedsSRE incident mgmtLesson #4
Google Cloud Service Health status page — Status page, customer notices, regulators and press; one voice, timed updates.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
- FM-05Give customers restoration times per product as each one recoversSRE incident mgmtCorrection of errors #7
Failure mode & effects analysis (FMEA)
The power chain (utility feeds, rotary UPS on each side, row transfer between feeds) and the cooling chain (chiller controller, chilled-water pumps, redundant source) of the facility hosting europe-west4-a, plus Google's thermal shutdown and recovery. Analysed from Google's own reports; the facility provider is not named and its view is not on record.
- Caught only after impactD ≥ 8
- 1 of 5
- Actions that cut occurrenceO lowered
- 3
- Actions that cut detectionD lowered
- 1
- Actions that cut severityblast radius unchanged
- 0
FM-04 The redundant source is out of service for known construction work when the primary plant stopsRedundant cooling source during construction 8·5·7 280 —
- Function
- Provide a second source of cooling if the primary plant stops
- Effect
- No fallback cooling; the single failure becomes a hall-wide thermal event
- Cause
- Planned degradation of cooling redundancy without a compensating measure in the record
- Prevention in place
- N+1 or 2N cooling design (degraded for construction)
- Detection in place
- Known to the facility; nothing recorded flagged the risk of running degraded
- S 8
- It removes the fallback that would have prevented the thermal event; scored 8 so the thermal outage is not counted at full weight twice.
- O 5
- Construction and maintenance windows recur through a facility's life: 'occasional'.
- D 7
- The degradation was known, but no recorded control weighed the exposure it created.
Corrective action
- None published — residual risk.
Who acts — playbook
- Operations lead Treat removal of cooling redundancy as a change with a compensating plan such as temporary chillers or reduced loadChange managementImprovement #6
- Mechanical / cooling engineer Watch supply temperature and flow continuously while cooling runs without redundancyASHRAE TC 9.9Lesson #3
- Incident commander Declare a thermal emergency early and start shutdown before the envelope is crossedNIMS / ICSLesson #5
- Vendor / upstream provider Restore the redundant source and confirm both loops before ending the emergencyUptime OSLesson #3
Evidence
- Reference #1 · official-postmortem“known ongoing construction work at the facility”
- Contributing factor #4The redundant cooling source was out of service because of known ongoing construction work (Google report).
- Sequence of events #3“The redundant cooling source is out of service because of known ongoing construction work”
FM-01 The DRUPS fails to take over the side A load because of electrical component failuresSide A diesel rotary UPS (DRUPS) 8·4·7 224 —
- Function
- Carry side A of the facility through a utility disturbance until diesel or utility power returns
- Effect
- Side A is lost; three rows must transfer to feed B, and one of them fails
- Cause
- Electrical component failures in the side A DRUPS; details not disclosed
- Prevention in place
- A rotary UPS on each side; automatic row transfer to the other feed
- Detection in place
- None recorded before the event; the failure showed only when the DRUPS was called on
- S 8
- It removes one whole power side; with the transfer scheme working it would have been survivable, so 8 rather than 9.
- O 4
- A rotary UPS failing at the moment of demand is uncommon but plausible: 'infrequent'.
- D 7
- No recorded test or alarm found the faulty components beforehand.
Corrective action
- Investigate the DRUPS transfer failure (Google, committed; completion not reported) Correction of errors #1
- Swing DRUPS in place while the faulty unit is repaired (facility team) Correction of errors #9
Who acts — playbook
- Authorised electrical person Load-test each rotary UPS on a schedule and after any component work, and track faults to closureNFPA 110Correction of errors #1
- First responder Confirm at the switchboard which side is on DRUPS and which has dropped within the first minuteUptime OSContributing factor #1
- Authorised electrical person Isolate the failed DRUPS and align a swing unit to restore redundancyEN 50110-1Correction of errors #9
- Vendor / upstream provider Repair the failed DRUPS components and prove the unit under load before returning it to serviceNFPA 110Correction of errors #9
Evidence
- Sequence of events #2“fails to take over the load because of electrical component failures”
- Contributing factor #1The side A DRUPS failed to take the load because of electrical component failures (Google report).
- Root cause“The side A DRUPS failed to take over the facility load due to electrical component failures”
FM-02 Row 3's transfer trips an overload protection breaker and the row loses both feedsRow 3 automatic transfer to feed B 7·4·8 224 126
- Function
- Move each row's load to the surviving feed when one feed is lost
- Effect
- Complete power loss to every rack in Row 3
- Cause
- Load deployment discrepancy: the row's load did not fit the surviving feed (under investigation)
- Prevention in place
- 2N distribution with automatic transfer between feeds
- Detection in place
- None recorded; the mismatch surfaced only on transfer
- S 7
- One row loses power completely; the hall-wide outage came from cooling, so this is scored 7.
- O 4
- Rows drifting past single-feed capacity is a known operational risk: 'infrequent'.
- D 8
- Nothing caught the discrepancy before the transfer was demanded.
Corrective action
- Find and resolve the overload cause (Google, committed; completion not reported) Correction of errors #2
After action: S7 · O3 · D6 → RPN 126. Committed but not reported complete: if the load discrepancy is found and per-row load is checked against single-feed capacity, both occurrence and detection improve. This is a claim about the action, not a confirmed result.
Who acts — playbook
- Operations lead Keep deployed load per row within what one feed can carry, and check it at every deploymentUptime OSCorrection of errors #2
- Authorised electrical person Alarm when any row's measured load exceeds single-feed capacityUptime OSLesson #4
- Authorised electrical person Once the fault is isolated, reset the tripped breakers and verify panels before re-energisingNFPA 70EContributing factor #2
- Service recovery lead Bring Row 3 workloads back in order and verify redundancy on both feedsSRE incident mgmtLesson #4
Evidence
- Sequence of events #6“Row 3 fails to transfer because an overload protection breaker trips”
- Contributing factor #2Row 3 tripped an overload protection breaker on transfer to feed B: a load deployment discrepancy, still under investigation (Google report).
- Metric #9Rows on feed A that had to transfer: 3; Rows 1 and 2 transferred, Row 3 lost power
FM-03 The chiller controller drops offline on the transient; pumps stop and do not restart, and chiller A shuts downChiller controller and chilled-water pumps 9·4·4 144 108
- Function
- Keep chilled water flowing to the data hall through a power disturbance
- Effect
- No chilled water to the hall; temperature reaches 44°C and equipment is shut down
- Cause
- Controller without ride-through on the transient; pumps depend on a restart command
- Prevention in place
- Chillers on power; redundant cooling source (unavailable at the time)
- Detection in place
- Remote monitoring alerted on high temperature at 16:32 and switch temperature alerts at 17:05
- S 9
- It forced a hall-wide thermal shutdown of every product in the zone's affected hall: 9. Not 10, because no hazard to people is recorded.
- O 4
- Controller dropouts on transients happen but are not frequent: 'infrequent'.
- D 4
- Temperature alerts came within minutes, but they did not stop the rise.
Corrective action
- Interim portable UPS for the chiller controllers (facility team, done) Correction of errors #8
- Investigate pump control redundancy (Google, committed; completion not reported) Correction of errors #3
After action: S9 · O3 · D4 → RPN 108. The portable UPS is in place, so the same transient should no longer drop the controller. It is an interim measure; the permanent pump-control review is committed but not reported complete.
Who acts — playbook
- Mechanical / cooling engineer Put chiller controllers on protected power and make pumps restart on their own after power returnsASHRAE TC 9.9Correction of errors #8
- Mechanical / cooling engineer Alarm on loss of chilled-water flow, not only on rising room temperatureASHRAE TC 9.9Lesson #2
- Mechanical / cooling engineer Switch pumps to hand mode to restore flow at once when the controller is downUptime OSLesson #2
- Service recovery lead Shut down equipment in priority order before the hall passes the allowable envelopeASHRAE TC 9.9Correction of errors #5
- Operations lead Restart workloads only after the hall is back inside the allowable rangeASHRAE TC 9.9Lesson #5
Evidence
- Sequence of events #3“the chilled-water distribution pumps stop and cannot restart”
- Metric #2Peak data hall temperature: 44°C at 18:29 PDT
- Contributing factor #3The chiller controller dropped offline on the transient and the distribution pumps did not restart on their own (Google report).
FM-05 Shutdown is manual and recovery needs an onsite technician for console serversThermal shutdown and recovery 7·5·3 105 84
- Function
- Protect equipment in a thermal event and bring services back quickly
- Effect
- Customer disruption lasts 14 hours 55 minutes, long after cooling returned at 21:05
- Cause
- Manual shutdown procedure; out-of-band console access needed physical recovery
- Prevention in place
- Cooling emergency shutdown procedure; NetApp clusters' automatic thermal shutdown
- Detection in place
- Monitoring and probers alerted within minutes
- S 7
- It stretches the outage for 33 customers well past the physical fix: 7.
- O 5
- Any thermal event needs shutdown and restart: 'occasional'.
- D 3
- Monitoring detected the problem quickly; the gap is in response speed.
Corrective action
- Automated shutdown during fast thermal runaway (GCVE, committed) Correction of errors #5
- Incident classification and staffing for major data center events (BMS, committed) Correction of errors #6
- Joint runbooks, monthly emergency drill, faster cluster recovery (NetApp Volumes, committed) Correction of errors #7
After action: S7 · O4 · D3 → RPN 84. Automation and drills should shorten the next event's tail; all three are committed but not reported complete.
Who acts — playbook
- Operations lead Trigger shutdown automatically on a temperature rate of rise, not only on a fixed thresholdASHRAE TC 9.9Correction of errors #5
- Service recovery lead Shut down in a set order so storage and network recover cleanlySRE incident mgmtCorrection of errors #7
- First responder Keep a technician on call for console servers during any major facility eventUptime OSCorrection of errors #6
- Communications lead Give customers restoration times per product as each one recoversSRE incident mgmtCorrection of errors #7
On the record at this failure
Evidence
- Sequence of events #17“Onsite technician arrived to recover the console servers”
- Metric #5Total customer disruption: 14 hours 55 minutes (16:39 15 Jul → 07:34 16 Jul PDT)
- Contributing factor #6Console servers needed an onsite technician to recover, which delayed network restoration after cooling returned (Google report, GCVE timeline).
Scoring rubric and method
Scales adapted from IEC 60812:2018 and AIAG-VDA. RPN = S × O × D. High: S ≥ 9 with O ≥ 4 or D ≥ 7, or RPN ≥ 300. Medium: RPN ≥ 120 or S ≥ 7. Severity overrides the product: 9 × 2 × 9 = 162 would otherwise hide a region-wide outage nothing could catch. Quotes are checked verbatim against this dossier; a revised score needs a published action. RZ analyst assessment, not an operator document.
Severity
| 10 | Hazard to people, or loss of the facility / several regions |
| 9 | Region-wide or provider-wide outage of a foundational service, no workaround |
| 8 | Full outage of a major service for hours |
| 7 | Major degradation of a major service |
| 6 | Partial outage confined to one zone or one service |
| 5 | Customer-visible degradation |
| 4 | Limited customer impact |
| 3 | Internal impact only |
| 2 | Negligible |
| 1 | No effect |
Occurrence
| 10 | Near certain: the cause is present in normal operation |
| 8 | Frequent: routine work exercises the cause |
| 6 | Occasional: a foreseeable slip or condition, weakly guarded |
| 4 | Infrequent: needs an unusual combination |
| 2 | Remote: guarded by design |
| 1 | Eliminated by design |
Detection
| 10 | No control could detect it |
| 9 | Detected only through customer impact |
| 8 | Detected after impact by internal monitoring |
| 6 | Detected at onset, not prevented |
| 4 | Detected before impact with time to act |
| 2 | Automated interlock almost certainly stops it |
| 1 | Certain to be stopped |
Root cause and contributing factors
Full root-cause narrative
Contributing factors by category
- The side A DRUPS failed to take the load because of electrical component failures (Google report).
- Row 3 tripped an overload protection breaker on transfer to feed B: a load deployment discrepancy, still under investigation (Google report).
- The chiller controller dropped offline on the transient and the distribution pumps did not restart on their own (Google report).
- The redundant cooling source was out of service because of known ongoing construction work (Google report).
- Chiller controllers apparently lacked protected power: the fix was an interim portable UPS for them (analyst inference from the action).
- Console servers needed an onsite technician to recover, which delayed network restoration after cooling returned (Google report, GCVE timeline).
- Thermal shutdown was a manual procedure; Google is now automating shutdown for fast-moving thermal events (Google report).
Analysis
One transient, three failures
A 3 ms dip should be a non-event for a site with two feeds, a rotary UPS on each side and redundant cooling. Here it found a failed DRUPS on side A, an overloaded row that could not move to side B, and a chiller controller with no ride-through while the second cooling source was out for construction. Each weakness alone would have been survivable.
Cooling failed through its controls
The chillers kept power. What stopped was the controller and therefore the pumps. The repair was to put the pumps in hand mode. Controls and pumps belong in the same protected-power and restart design as the chillers, or cooling capacity on paper is not capacity in an event.
Construction as a hidden degradation
The redundant cooling source was out for known construction work. Planned degradation is common, but the record shows no compensating measure for the window, and the event happened inside it.
Speed of a thermal event
From transient to 44°C took about two hours; NetApp clusters shut themselves down after about an hour. Google ran manual shutdown procedures and is now automating them, and is changing incident classification so enough people are available during major data center events.
What the record does not say
The report does not name the data center provider, the DRUPS make or the failed components, the chiller or pump models, or the cost. It also does not say whether the committed actions due in August to October 2026 have been completed.
Technical deep-dive
Corrective actions and lessons
Correction of errors
| Action | Owner | Status |
|---|---|---|
| Investigate the sequence that stopped the load transfer to DRUPS and identify system improvements | Google with the data center provider | Committed, ETA Aug 2026 (completion not reported) |
| Find and resolve the cause of the overload that cut power to Row 3 | Committed, ETA Aug 2026 (completion not reported) | |
| Investigate chiller pump control redundancy to make the cooling system resilient | Google with the data center provider | Committed, ETA Sep 2026 (completion not reported) |
| Improve facility monitoring alerts for power events and set early thresholds for cooling excursions | Committed, ETA Aug 2026 (completion not reported) | |
| Automate shutdown triggering during fast thermal runaway for VMware Engine | Google Cloud (GCVE) | Committed, ETA Oct 2026 (completion not reported) |
| Update incident classification and SLO definitions to improve personnel availability during major data center events | Google Cloud (BMS) | Committed, ETA Sep 2026 (completion not reported) |
| Review incident SLAs and runbooks with the data center team, create playbooks, run a monthly joint emergency drill and speed up NetApp cluster recovery | Google Cloud (NetApp Volumes) | Committed, ETA Aug 2026 (completion not reported) |
| Interim portable UPS to keep the chiller controllers powered | Facility team | Done, stated in the report |
| Swing DRUPS unit aligned to restore feed A redundancy while the faulty DRUPS is repaired | Facility team | Swing unit in place; repair in progress at the time of the report |
Lessons learnt
- A cooling plant's controls are part of the critical load. If a 3 ms transient can drop the chiller controller, the cooling plant has no ride-through no matter how much the chillers can do.
- Pumps that need a restart command after a power event are a single point of failure; restart-on-power-return or hand-mode fallback must be designed in and drilled.
- Taking cooling redundancy out for construction turns the next routine event into a thermal emergency. Plan compensating measures for the construction window.
- Automatic transfer schemes only work if each row's load fits the surviving feed. Track deployed load per row against single-feed capacity.
- Thermal events move fast: 44°C two hours after the trigger. Shutdown triggers and onsite staffing must be faster than the temperature rise.
- Recovery depends on out-of-band access: needing a technician on site for console servers lengthened the outage after cooling returned.
Improvements
- Safety and cooling: keep chiller controllers on protected power (interim portable UPS done) and review pump control redundancy (Google committed).
- Designinvestigate the DRUPS transfer failure and restore full A-side redundancy (swing DRUPS in place; investigation committed).
- Designresolve the Row 3 overload so every row fits one surviving feed (Google committed).
- Monitoring: earlier alerts for power events and cooling excursions (Google committed).
- Processautomated shutdown for fast thermal runaway, updated incident classification for staffing, joint runbooks and a monthly emergency drill with the data center team (Google committed).
- Analyst recommendation (not in the report): treat removal of cooling redundancy for construction as a change that needs a compensating plan, such as temporary chillers or reduced load.
References and provenance
- official-postmortem Google Cloud Service Health, incident 3BvH3LVGcupoYqV6F4Nw, final incident report (25 Jul 2026)“The redundant source was not available due to known ongoing construction work at the facility.”https://status.cloud.google.com/incidents/3BvH3LVGcupoYqV6F4Nw
- vendor-status Google Cloud Service Health, incident 3BvH3LVGcupoYqV6F4Nw, preliminary incident report (17 Jul 2026)“experienced a loss of utility power and subsequent cooling capacity”https://status.cloud.google.com/incidents/3BvH3LVGcupoYqV6F4Nw
Quotes are short, attributed, and for provenance only; the analysis is original. Last verified 2026-11-11.