← All incidents
Incident dossier · Rank #43 · magnitude 4.7

Google Cloud europe-west4-a: Grid Transient, DRUPS Failure and Chiller Shutdown

Google Cloud (data center provider not named) 2026-07-15 14h 55m to substantial restoration PowerCooling

Summary

On 15 July 2026 a 3 ms grid transient tripped both utility feeds at the facility hosting Google Cloud zone europe-west4-a. The side A rotary UPS failed, one row lost power on transfer, and the chiller controller dropped out so the pumps stopped while the backup cooling was out for construction. The hall reached 44°C and equipment was shut down; customer disruption lasted 14 hours 55 minutes.

Users affected
24 VMware Engine private clouds of 20 customers, 9 Bare Metal Solution customers, and NetApp Volumes customers on all 6 clusters in europe-west4-a.
Duration
14h 55m — Customer disruption from 16:39 PDT 15 Jul → 07:34 PDT 16 Jul (14 h 55 min)
Financial
Not disclosed
Scope
Single data hall: power loss to one row and hall-wide thermal shutdown
Site
Facility hosting zone europe-west4-a · Site not named, Netherlands, europe-west4-a
Services down
Google Cloud VMware Engine, Bare Metal Solution, Google Cloud NetApp Volumes

How the defences failed

How the defences failed — Google Cloud5 failure modes in the order the sequence of events first shows them, 0 latent conditions with no moment in the record, ending in the outcome: Hall at 44°C · 14 h 55 min.ACTIVE — IN THE ORDER THE RECORD SHOWS THEMFM-01 · RPN 224DRUPS A failsS8 · O4 · D7FM-03 · RPN 144Chiller pumps stopS9 · O4 · D4FM-04 · RPN 280Backup cooling offlineS8 · O5 · D7FM-02 · RPN 224Row 3 overload tripS7 · O4 · D8FM-05 · RPN 105Slow thermal recoveryS7 · O5 · D3OUTCOMEHall at 44°C · 14 h 55 minLEGENDMedium or low priorityHigh priorityMedium or low priority, no published actionNext failure in the record
How the defences failed — Google Cloud5 failure modes in the order the sequence of events first shows them, 0 latent conditions with no moment in the record, ending in the outcome: Hall at 44°C · 14 h 55 min.ACTIVE — RECORD ORDERFM-01 · RPN 224DRUPS A failsS8 · O4 · D7FM-03 · RPN 144Chiller pumps stopS9 · O4 · D4FM-04 · RPN 280Backup cooling offlineS8 · O5 · D7FM-02 · RPN 224Row 3 overload tripS7 · O4 · D8FM-05 · RPN 105Slow thermal recoveryS7 · O5 · D3OUTCOMEHall at 44°C · 14 h 55 minLEGENDMedium or low priorityHigh priorityMedium or low priority, no published actionNext failure in the record
Every failure mode of the FMEA below. Active modes run in the order the sequence of events first shows them — record order, not a proof of cause; latent modes were in place before the event. Red outline: high priority. Dashed: no published corrective action.
Magnitude sub-scores (0–10)Magnitude sub-scores (0–10)Users 5Users affected (0–10) — breadth of the user/customer population impacted. — scored 5/10.Financial 4Financial impact (0–10) — direct + consequential cost. — scored 4/10.Duration 6Outage duration (0–10), from the measured duration by fixed bands: <1 h 3 · 1–4 h 4 · 4–12 h 5 · 12–24 h 6 · 1–3 d 7 · 3–7 d 8 · 7–30 d 9 · >30 d 10; no customer downtime 1. — scored 6/10.Blast 4Blast radius (0–10) — how wide the fault propagated across systems/regions. — scored 4/10.
Magnitude 4.7 = blast 4×0.35 + users 5×0.25 + financial 4×0.20 + duration 6×0.20 (sub-scores 0–10 · weighted composite)

One data hall serving three specialised products; 33 named customers plus NetApp Volumes users. Duration (6): 14 h 55 min, inside the 12–24 h band. No cost is disclosed, so financial is judged moderate.

All 9 impact metrics
Utility voltage transient3 ms, on both feeds A and B
Peak data hall temperature44°C at 18:29 PDT
Power event to 44°C2 hours 5 minutes (16:24 → 18:29 PDT)
Cooling lostabout 4 hours 41 minutes (16:24 → 21:05 PDT)
Total customer disruption14 hours 55 minutes (16:39 15 Jul → 07:34 16 Jul PDT)
VMware Engine customers affected24 private clouds of 20 customers
Bare Metal Solution customers affected9 customers
NetApp clusters shut downall 6
Rows on feed A that had to transfer3; Rows 1 and 2 transferred, Row 3 lost power

Sequence of events

  1. TRIGGER An electrical fault occurred on the utility grid upstream of the data center: a 3 ms voltage transient hits both utility feeds A and B, both utility breakers trip and the site transfers to its diesel rotary UPS (DRUPS).Utility / grid operator
  2. TRIGGER Side B transfers to DRUPS without interruption. The DRUPS for side A fails to take over the load because of electrical component failures.
  3. TRIGGER The chiller controller drops offline during the transient, so the chilled-water distribution pumps stop and cannot restart and chiller system A shuts down. The redundant cooling source is out of service because of known ongoing construction work.
  4. DETECTION Google engineers were alerted to the infrastructure power loss by automated monitoring; the VMware Engine power-monitoring alert fires.Operations lead
  5. DETECTION NetApp's remote facility monitoring alerts on high temperature and network switch failure.
  6. CASCADE The three rows on feed A transfer to feed B. Rows 1 and 2 transfer; Row 3 fails to transfer because an overload protection breaker trips, and loses both feeds.
  7. IMPACT Customer disruption begins in europe-west4-a for VMware Engine, Bare Metal Solution and NetApp Volumes.
  8. IMPACT Network switch temperature alerts above 60°C trigger as the hall heats without chilled-water flow.
  9. CASCADE All 6 NetApp clusters shut down automatically because of high temperature.
  10. IMPACT Data hall temperatures reach 44°C and cross the safe machine operating threshold.
  11. CASCADE Four NetApp SAN storage nodes serving Bare Metal Solution fail and shut down from overheating; the first customer server shutdown follows.
  12. MITIGATION Google engineers start machine shutdown procedures for the reachable devices as part of the cooling emergency shutdown; all reachable server and network devices are off by 19:55.Service recovery lead
  13. MITIGATION The facility team switched the distribution pumps from auto to hand mode to restore circulation and cooling, and deployed an interim portable UPS to keep the chiller controllers powered.Mechanical / cooling engineer
  14. RECOVERY The cooling system is fully recovered and data hall temperatures return to the normal operating range.
  15. RECOVERY Notification about cooling recovery sent by provider at 21:24, followed by the power recovery notice at 21:46.Vendor / upstream provider
  16. RECOVERY With the fault isolated, teams reset the tripped breakers to re-energise Row 3; two remote power panels needed manual verification, and a swing DRUPS unit was aligned to restore redundancy on feed A.Authorised electrical person
  17. RECOVERY Onsite technician arrived to recover the console servers; console recovery completes at 23:10.First responder
  18. RECOVERY All 6 NetApp clusters and their customers are recovered and validated.
  19. RECOVERY VMware Engine incident mitigated: all customer private clouds are healthy.
  20. RESTORED End of the customer disruption window across the affected products in europe-west4-a.
  21. RESTORED Bare Metal Solution mitigated: every impacted customer server rebooted and confirmed healthy.

Response by role

9 roles/7 recorded actions/21 playbook actions across 5 failure modes/no recorded action: Incident commander, Communications lead

What each role did

Roles the sequence of events shows acting; every entry quotes its source line. Select a time to jump to it.

Role
Detect
Contain
Recover
Utility / grid operatorThe grid operator upstream of the facility, not named
no record
no record
Vendor / upstream providerThe data center provider operating the facility, not named
no record
no record
Authorised electrical personThe facility team that reset breakers and aligned a swing DRUPS, not named
no record
no record
Mechanical / cooling engineerThe facility team that put the pumps in hand mode, not named
no record
no record
First responderThe onsite technician who recovered the console servers
no record
no record
Operations leadGoogle engineers alerted by automated monitoring
no record
no record
Service recovery leadGoogle and NetApp teams shutting down and restoring equipment
no record
no record

Role by role

Recorded actions / playbook actions per role. A role with 0 recorded actions does not appear in the sources.

The grid operator upstream of the facility, not named — External owner of the supply: switching at the substation, load shedding, restoration.

On the record

  1. Grid fault upstream caused the 3 ms transient on both feedsAn electrical fault occurred on the utility grid upstream of the data center

Playbook analyst guidance by failure mode, not a record of what happened

The data center provider operating the facility, not named — Third party whose product, service or network sits in the failure path.

On the record

  1. Notified recovery of cooling and then powerNotification about cooling recovery sent by provider

Playbook analyst guidance by failure mode, not a record of what happened

Recover
  • FM-04Restore the redundant source and confirm both loops before ending the emergencyUptime OSLesson #3
  • FM-01Repair the failed DRUPS components and prove the unit under load before returning it to serviceNFPA 110Correction of errors #9

The facility team that reset breakers and aligned a swing DRUPS, not named — Switching, isolation and lock-out of power sources, and safe re-energisation.

On the record

  1. Re-energised Row 3 after isolating the fault and aligned a swing DRUPSteams reset the tripped breakers to re-energise Row 3

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-01Load-test each rotary UPS on a schedule and after any component work, and track faults to closureNFPA 110Correction of errors #1
Detect
  • FM-02Alarm when any row's measured load exceeds single-feed capacityUptime OSLesson #4
Contain
  • FM-01Isolate the failed DRUPS and align a swing unit to restore redundancyEN 50110-1Correction of errors #9
  • FM-02Once the fault is isolated, reset the tripped breakers and verify panels before re-energisingNFPA 70EContributing factor #2

The facility team that put the pumps in hand mode, not named — Chillers, CRAH/CRAC, pumps, cooling towers and the thermal envelope of the white space.

On the record

  1. Restored chilled-water circulation by running the pumps in hand modeswitched the distribution pumps from auto to hand mode

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-03Put chiller controllers on protected power and make pumps restart on their own after power returnsASHRAE TC 9.9Correction of errors #8
Detect
  • FM-04Watch supply temperature and flow continuously while cooling runs without redundancyASHRAE TC 9.9Lesson #3
  • FM-03Alarm on loss of chilled-water flow, not only on rising room temperatureASHRAE TC 9.9Lesson #2
Contain
  • FM-03Switch pumps to hand mode to restore flow at once when the controller is downUptime OSLesson #2

The onsite technician who recovered the console servers — Meets the first alarm: on-shift technician or security in a facility, on-call engineer in a service.

On the record

  1. Recovered the console servers on siteOnsite technician arrived to recover the console servers

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-01Confirm at the switchboard which side is on DRUPS and which has dropped within the first minuteUptime OSContributing factor #1
Recover
  • FM-05Keep a technician on call for console servers during any major facility eventUptime OSCorrection of errors #6

No incident commander is named in the record — Owns every decision until formally relieved: site duty manager on scene, or the declared IC of a service incident.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Contain
  • FM-04Declare a thermal emergency early and start shutdown before the envelope is crossedNIMS / ICSLesson #5

Google engineers alerted by automated monitoring — Technical lead who diagnoses and drives the fix; the subject-matter expert at the keyboard or the switchboard.

On the record

  1. Alerted by monitoring six minutes after the transientGoogle engineers were alerted to the infrastructure power loss

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-04Treat removal of cooling redundancy as a change with a compensating plan such as temporary chillers or reduced loadChange managementImprovement #6
  • FM-02Keep deployed load per row within what one feed can carry, and check it at every deploymentUptime OSCorrection of errors #2
Detect
  • FM-05Trigger shutdown automatically on a temperature rate of rise, not only on a fixed thresholdASHRAE TC 9.9Correction of errors #5
Recover
  • FM-03Restart workloads only after the hall is back inside the allowable rangeASHRAE TC 9.9Lesson #5

Google and NetApp teams shutting down and restoring equipment — Restores customer service: failover, workload moves, capacity, backlog drain.

On the record

  1. Ran the cooling emergency shutdown for reachable devicesstart machine shutdown procedures for the reachable devices

Playbook analyst guidance by failure mode, not a record of what happened

Contain
  • FM-03Shut down equipment in priority order before the hall passes the allowable envelopeASHRAE TC 9.9Correction of errors #5
  • FM-05Shut down in a set order so storage and network recover cleanlySRE incident mgmtCorrection of errors #7
Recover
  • FM-02Bring Row 3 workloads back in order and verify redundancy on both feedsSRE incident mgmtLesson #4

Google Cloud Service Health status page — Status page, customer notices, regulators and press; one voice, timed updates.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Recover
  • FM-05Give customers restoration times per product as each one recoversSRE incident mgmtCorrection of errors #7

Failure mode & effects analysis (FMEA)

The power chain (utility feeds, rotary UPS on each side, row transfer between feeds) and the cooling chain (chiller controller, chilled-water pumps, redundant source) of the facility hosting europe-west4-a, plus Google's thermal shutdown and recovery. Analysed from Google's own reports; the facility provider is not named and its view is not on record.

5 failure modes/1 high priority/3 of 5 with a published action/total RPN 977 → 822 (−16%)

RPN = S × O × D, worst first. Thin bar: after the published action.
FM-04no published action280
FM-01no published action224
FM-02224 → 126
FM-03144 → 108
FM-05105 → 84
Severity × occurrence. Lines bound the medium and high zones.
1122334455667788991010Occurrence →Severity →FM-03 The chiller controller drops offline on the transient; pumps stop and do not restart, and chiller A shuts down (S9 O4 D4)03FM-01 The DRUPS fails to take over the side A load because of electrical component failures (S8 O4 D7)01FM-04 The redundant source is out of service for known construction work when the primary plant stops (S8 O5 D7)04FM-02 Row 3's transfer trips an overload protection breaker and the row loses both feeds (S7 O4 D8)02FM-05 Shutdown is manual and recovery needs an onsite technician for console servers (S7 O5 D3)05
Caught only after impactD ≥ 8
1 of 5
Actions that cut occurrenceO lowered
3
Actions that cut detectionD lowered
1
Actions that cut severityblast radius unchanged
0
FM-04 The redundant source is out of service for known construction work when the primary plant stopsRedundant cooling source during construction 8·5·7 280 —
Function
Provide a second source of cooling if the primary plant stops
Effect
No fallback cooling; the single failure becomes a hall-wide thermal event
Cause
Planned degradation of cooling redundancy without a compensating measure in the record
Prevention in place
N+1 or 2N cooling design (degraded for construction)
Detection in place
Known to the facility; nothing recorded flagged the risk of running degraded
S 8
It removes the fallback that would have prevented the thermal event; scored 8 so the thermal outage is not counted at full weight twice.
O 5
Construction and maintenance windows recur through a facility's life: 'occasional'.
D 7
The degradation was known, but no recorded control weighed the exposure it created.

Corrective action

  • None published — residual risk.

Who acts — playbook

Prevent
  • Operations lead Treat removal of cooling redundancy as a change with a compensating plan such as temporary chillers or reduced loadChange managementImprovement #6
Detect
  • Mechanical / cooling engineer Watch supply temperature and flow continuously while cooling runs without redundancyASHRAE TC 9.9Lesson #3
Contain
  • Incident commander Declare a thermal emergency early and start shutdown before the envelope is crossedNIMS / ICSLesson #5
Recover
  • Vendor / upstream provider Restore the redundant source and confirm both loops before ending the emergencyUptime OSLesson #3

Evidence

  • Reference #1 · official-postmortem“known ongoing construction work at the facility”
  • Contributing factor #4The redundant cooling source was out of service because of known ongoing construction work (Google report).
  • Sequence of events #3“The redundant cooling source is out of service because of known ongoing construction work”
FM-01 The DRUPS fails to take over the side A load because of electrical component failuresSide A diesel rotary UPS (DRUPS) 8·4·7 224 —
Function
Carry side A of the facility through a utility disturbance until diesel or utility power returns
Effect
Side A is lost; three rows must transfer to feed B, and one of them fails
Cause
Electrical component failures in the side A DRUPS; details not disclosed
Prevention in place
A rotary UPS on each side; automatic row transfer to the other feed
Detection in place
None recorded before the event; the failure showed only when the DRUPS was called on
S 8
It removes one whole power side; with the transfer scheme working it would have been survivable, so 8 rather than 9.
O 4
A rotary UPS failing at the moment of demand is uncommon but plausible: 'infrequent'.
D 7
No recorded test or alarm found the faulty components beforehand.

Corrective action

  • Investigate the DRUPS transfer failure (Google, committed; completion not reported) Correction of errors #1
  • Swing DRUPS in place while the faulty unit is repaired (facility team) Correction of errors #9

Who acts — playbook

Prevent
  • Authorised electrical person Load-test each rotary UPS on a schedule and after any component work, and track faults to closureNFPA 110Correction of errors #1
Detect
  • First responder Confirm at the switchboard which side is on DRUPS and which has dropped within the first minuteUptime OSContributing factor #1
Contain
  • Authorised electrical person Isolate the failed DRUPS and align a swing unit to restore redundancyEN 50110-1Correction of errors #9
Recover
  • Vendor / upstream provider Repair the failed DRUPS components and prove the unit under load before returning it to serviceNFPA 110Correction of errors #9

Evidence

  • Sequence of events #2“fails to take over the load because of electrical component failures”
  • Contributing factor #1The side A DRUPS failed to take the load because of electrical component failures (Google report).
  • Root cause“The side A DRUPS failed to take over the facility load due to electrical component failures”
FM-02 Row 3's transfer trips an overload protection breaker and the row loses both feedsRow 3 automatic transfer to feed B 7·4·8 224 126
Function
Move each row's load to the surviving feed when one feed is lost
Effect
Complete power loss to every rack in Row 3
Cause
Load deployment discrepancy: the row's load did not fit the surviving feed (under investigation)
Prevention in place
2N distribution with automatic transfer between feeds
Detection in place
None recorded; the mismatch surfaced only on transfer
S 7
One row loses power completely; the hall-wide outage came from cooling, so this is scored 7.
O 4
Rows drifting past single-feed capacity is a known operational risk: 'infrequent'.
D 8
Nothing caught the discrepancy before the transfer was demanded.

Corrective action

  • Find and resolve the overload cause (Google, committed; completion not reported) Correction of errors #2

After action: S7 · O3 · D6 → RPN 126. Committed but not reported complete: if the load discrepancy is found and per-row load is checked against single-feed capacity, both occurrence and detection improve. This is a claim about the action, not a confirmed result.

Who acts — playbook

Prevent
  • Operations lead Keep deployed load per row within what one feed can carry, and check it at every deploymentUptime OSCorrection of errors #2
Detect
  • Authorised electrical person Alarm when any row's measured load exceeds single-feed capacityUptime OSLesson #4
Contain
  • Authorised electrical person Once the fault is isolated, reset the tripped breakers and verify panels before re-energisingNFPA 70EContributing factor #2
Recover
  • Service recovery lead Bring Row 3 workloads back in order and verify redundancy on both feedsSRE incident mgmtLesson #4

Evidence

  • Sequence of events #6“Row 3 fails to transfer because an overload protection breaker trips”
  • Contributing factor #2Row 3 tripped an overload protection breaker on transfer to feed B: a load deployment discrepancy, still under investigation (Google report).
  • Metric #9Rows on feed A that had to transfer: 3; Rows 1 and 2 transferred, Row 3 lost power
FM-03 The chiller controller drops offline on the transient; pumps stop and do not restart, and chiller A shuts downChiller controller and chilled-water pumps 9·4·4 144 108
Function
Keep chilled water flowing to the data hall through a power disturbance
Effect
No chilled water to the hall; temperature reaches 44°C and equipment is shut down
Cause
Controller without ride-through on the transient; pumps depend on a restart command
Prevention in place
Chillers on power; redundant cooling source (unavailable at the time)
Detection in place
Remote monitoring alerted on high temperature at 16:32 and switch temperature alerts at 17:05
S 9
It forced a hall-wide thermal shutdown of every product in the zone's affected hall: 9. Not 10, because no hazard to people is recorded.
O 4
Controller dropouts on transients happen but are not frequent: 'infrequent'.
D 4
Temperature alerts came within minutes, but they did not stop the rise.

Corrective action

  • Interim portable UPS for the chiller controllers (facility team, done) Correction of errors #8
  • Investigate pump control redundancy (Google, committed; completion not reported) Correction of errors #3

After action: S9 · O3 · D4 → RPN 108. The portable UPS is in place, so the same transient should no longer drop the controller. It is an interim measure; the permanent pump-control review is committed but not reported complete.

Who acts — playbook

Prevent
  • Mechanical / cooling engineer Put chiller controllers on protected power and make pumps restart on their own after power returnsASHRAE TC 9.9Correction of errors #8
Detect
  • Mechanical / cooling engineer Alarm on loss of chilled-water flow, not only on rising room temperatureASHRAE TC 9.9Lesson #2
Contain
  • Mechanical / cooling engineer Switch pumps to hand mode to restore flow at once when the controller is downUptime OSLesson #2
  • Service recovery lead Shut down equipment in priority order before the hall passes the allowable envelopeASHRAE TC 9.9Correction of errors #5
Recover
  • Operations lead Restart workloads only after the hall is back inside the allowable rangeASHRAE TC 9.9Lesson #5

Evidence

  • Sequence of events #3“the chilled-water distribution pumps stop and cannot restart”
  • Metric #2Peak data hall temperature: 44°C at 18:29 PDT
  • Contributing factor #3The chiller controller dropped offline on the transient and the distribution pumps did not restart on their own (Google report).
FM-05 Shutdown is manual and recovery needs an onsite technician for console serversThermal shutdown and recovery 7·5·3 105 84
Function
Protect equipment in a thermal event and bring services back quickly
Effect
Customer disruption lasts 14 hours 55 minutes, long after cooling returned at 21:05
Cause
Manual shutdown procedure; out-of-band console access needed physical recovery
Prevention in place
Cooling emergency shutdown procedure; NetApp clusters' automatic thermal shutdown
Detection in place
Monitoring and probers alerted within minutes
S 7
It stretches the outage for 33 customers well past the physical fix: 7.
O 5
Any thermal event needs shutdown and restart: 'occasional'.
D 3
Monitoring detected the problem quickly; the gap is in response speed.

Corrective action

  • Automated shutdown during fast thermal runaway (GCVE, committed) Correction of errors #5
  • Incident classification and staffing for major data center events (BMS, committed) Correction of errors #6
  • Joint runbooks, monthly emergency drill, faster cluster recovery (NetApp Volumes, committed) Correction of errors #7

After action: S7 · O4 · D3 → RPN 84. Automation and drills should shorten the next event's tail; all three are committed but not reported complete.

Who acts — playbook

Detect
  • Operations lead Trigger shutdown automatically on a temperature rate of rise, not only on a fixed thresholdASHRAE TC 9.9Correction of errors #5
Contain
  • Service recovery lead Shut down in a set order so storage and network recover cleanlySRE incident mgmtCorrection of errors #7
Recover
  • First responder Keep a technician on call for console servers during any major facility eventUptime OSCorrection of errors #6
  • Communications lead Give customers restoration times per product as each one recoversSRE incident mgmtCorrection of errors #7

On the record at this failure

Evidence

  • Sequence of events #17“Onsite technician arrived to recover the console servers”
  • Metric #5Total customer disruption: 14 hours 55 minutes (16:39 15 Jul → 07:34 16 Jul PDT)
  • Contributing factor #6Console servers needed an onsite technician to recover, which delayed network restoration after cooling returned (Google report, GCVE timeline).
Scoring rubric and method

Scales adapted from IEC 60812:2018 and AIAG-VDA. RPN = S × O × D. High: S ≥ 9 with O ≥ 4 or D ≥ 7, or RPN ≥ 300. Medium: RPN ≥ 120 or S ≥ 7. Severity overrides the product: 9 × 2 × 9 = 162 would otherwise hide a region-wide outage nothing could catch. Quotes are checked verbatim against this dossier; a revised score needs a published action. RZ analyst assessment, not an operator document.

Severity

10Hazard to people, or loss of the facility / several regions
9Region-wide or provider-wide outage of a foundational service, no workaround
8Full outage of a major service for hours
7Major degradation of a major service
6Partial outage confined to one zone or one service
5Customer-visible degradation
4Limited customer impact
3Internal impact only
2Negligible
1No effect

Occurrence

10Near certain: the cause is present in normal operation
8Frequent: routine work exercises the cause
6Occasional: a foreseeable slip or condition, weakly guarded
4Infrequent: needs an unusual combination
2Remote: guarded by design
1Eliminated by design

Detection

10No control could detect it
9Detected only through customer impact
8Detected after impact by internal monitoring
6Detected at onset, not prevented
4Detected before impact with time to act
2Automated interlock almost certainly stops it
1Certain to be stopped

Root cause and contributing factors

TRIGGER: a 3 ms voltage transient on the utility grid upstream of the data center hosting europe-west4-a tripped the utility breakers on both feeds A and B at 16:24 PDT on 15 July 2026, and the site transferred to its diesel rotary UPS (DRUPS). POWER CHAIN: side B went to DRUPS cleanly. The side A DRUPS failed to take over the facility load due to electrical component failures, so the three rows on feed A had to transfer automatically to feed B. Two rows did.
Full root-cause narrative
Row 3 hit an overload protection breaker trip and lost both feeds; Google attributes this to a load deployment discrepancy, still under investigation at the time of the report. COOLING CHAIN: the same transient knocked the chiller controller offline. The chillers kept power but the chilled-water distribution pumps stopped and could not restart, so with no water flow chiller system A shut down. The redundant cooling source was unavailable because of known ongoing construction work at the facility. The hall reached 44°C two hours later and the equipment had to be shut down. LATENT ROOT: three independent weaknesses lined up on one transient: a DRUPS that could not carry its load, a row whose load did not fit the surviving feed, and a cooling plant whose controls had no ride-through and whose redundancy had been removed for construction. The facility team's own fix, a portable UPS for the chiller controllers, indicates the controllers were not on protected power (analyst inference from the action taken).

Contributing factors by category

Contributing factors by category — Google CloudEquipment: DRUPS A fails; Chiller controller drops. Design: Row 3 over one feed; Controls unprotected. Process: Manual thermal shutdown; Console needs technician. Environment: Cooling backup offline. External: 3 ms grid transient. Effect: europe-west4-a hall shut down.europe-west4-a hall shut downEquipmentDRUPS A failsChiller controller dropsProcessManual thermal shutdownConsole needs technicianExternal3 ms grid transientDesignRow 3 over one feedControls unprotectedEnvironmentCooling backup offline
Each short label stands for a contributing factor or failure mode recorded in this dossier; the full sentences are listed below.
  • The side A DRUPS failed to take the load because of electrical component failures (Google report).
  • Row 3 tripped an overload protection breaker on transfer to feed B: a load deployment discrepancy, still under investigation (Google report).
  • The chiller controller dropped offline on the transient and the distribution pumps did not restart on their own (Google report).
  • The redundant cooling source was out of service because of known ongoing construction work (Google report).
  • Chiller controllers apparently lacked protected power: the fix was an interim portable UPS for them (analyst inference from the action).
  • Console servers needed an onsite technician to recover, which delayed network restoration after cooling returned (Google report, GCVE timeline).
  • Thermal shutdown was a manual procedure; Google is now automating shutdown for fast-moving thermal events (Google report).

Analysis

One transient, three failures

A 3 ms dip should be a non-event for a site with two feeds, a rotary UPS on each side and redundant cooling. Here it found a failed DRUPS on side A, an overloaded row that could not move to side B, and a chiller controller with no ride-through while the second cooling source was out for construction. Each weakness alone would have been survivable.

Cooling failed through its controls

The chillers kept power. What stopped was the controller and therefore the pumps. The repair was to put the pumps in hand mode. Controls and pumps belong in the same protected-power and restart design as the chillers, or cooling capacity on paper is not capacity in an event.

Construction as a hidden degradation

The redundant cooling source was out for known construction work. Planned degradation is common, but the record shows no compensating measure for the window, and the event happened inside it.

Speed of a thermal event

From transient to 44°C took about two hours; NetApp clusters shut themselves down after about an hour. Google ran manual shutdown procedures and is now automating them, and is changing incident classification so enough people are available during major data center events.

What the record does not say

The report does not name the data center provider, the DRUPS make or the failed components, the chiller or pump models, or the cost. It also does not say whether the committed actions due in August to October 2026 have been completed.

Technical deep-dive
A rotary UPS bridges the gap to diesel with a flywheel; if its electrical components fail, the side it protects drops to the automatic transfer scheme. That scheme only works if every row's load fits the surviving feed: Row 3 tripped its overload protection, the textbook symptom of a row loaded beyond what one feed can carry alone (Google calls it a load deployment discrepancy). The cooling failure is a controls failure, not a chiller failure. A brief transient reset or dropped the chiller controller; the pumps needed a restart command that never came. The quick fix was mechanical: pumps put in hand mode. With the redundant source out for construction there was no second loop, so the hall rose to 44°C in about two hours and Google shut down reachable equipment. Recovery then needed an onsite technician for console servers, which added time after cooling was back at 21:05.

Corrective actions and lessons

Correction of errors

ActionOwnerStatus
Investigate the sequence that stopped the load transfer to DRUPS and identify system improvementsGoogle with the data center providerCommitted, ETA Aug 2026 (completion not reported)
Find and resolve the cause of the overload that cut power to Row 3GoogleCommitted, ETA Aug 2026 (completion not reported)
Investigate chiller pump control redundancy to make the cooling system resilientGoogle with the data center providerCommitted, ETA Sep 2026 (completion not reported)
Improve facility monitoring alerts for power events and set early thresholds for cooling excursionsGoogleCommitted, ETA Aug 2026 (completion not reported)
Automate shutdown triggering during fast thermal runaway for VMware EngineGoogle Cloud (GCVE)Committed, ETA Oct 2026 (completion not reported)
Update incident classification and SLO definitions to improve personnel availability during major data center eventsGoogle Cloud (BMS)Committed, ETA Sep 2026 (completion not reported)
Review incident SLAs and runbooks with the data center team, create playbooks, run a monthly joint emergency drill and speed up NetApp cluster recoveryGoogle Cloud (NetApp Volumes)Committed, ETA Aug 2026 (completion not reported)
Interim portable UPS to keep the chiller controllers poweredFacility teamDone, stated in the report
Swing DRUPS unit aligned to restore feed A redundancy while the faulty DRUPS is repairedFacility teamSwing unit in place; repair in progress at the time of the report

Lessons learnt

  • A cooling plant's controls are part of the critical load. If a 3 ms transient can drop the chiller controller, the cooling plant has no ride-through no matter how much the chillers can do.
  • Pumps that need a restart command after a power event are a single point of failure; restart-on-power-return or hand-mode fallback must be designed in and drilled.
  • Taking cooling redundancy out for construction turns the next routine event into a thermal emergency. Plan compensating measures for the construction window.
  • Automatic transfer schemes only work if each row's load fits the surviving feed. Track deployed load per row against single-feed capacity.
  • Thermal events move fast: 44°C two hours after the trigger. Shutdown triggers and onsite staffing must be faster than the temperature rise.
  • Recovery depends on out-of-band access: needing a technician on site for console servers lengthened the outage after cooling returned.

Improvements

  • Safety and cooling: keep chiller controllers on protected power (interim portable UPS done) and review pump control redundancy (Google committed).
  • Designinvestigate the DRUPS transfer failure and restore full A-side redundancy (swing DRUPS in place; investigation committed).
  • Designresolve the Row 3 overload so every row fits one surviving feed (Google committed).
  • Monitoring: earlier alerts for power events and cooling excursions (Google committed).
  • Processautomated shutdown for fast thermal runaway, updated incident classification for staffing, joint runbooks and a monthly emergency drill with the data center team (Google committed).
  • Analyst recommendation (not in the report): treat removal of cooling redundancy for construction as a change that needs a compensating plan, such as temporary chillers or reduced load.

References and provenance

Quotes are short, attributed, and for provenance only; the analysis is original. Last verified 2026-11-11.

Root access required

The DC Incidents dossier is a root-only module. Sign in with an authorized account to continue.

Back to Home