NorthC Almere Data Center Fire: A Compartment Blaze That Took Out the Facility Power Plant and Rippled Across Dutch Public Services
Summary
On 7 May 2026 (around 08:45 local time) a fire broke out in a rear technical compartment of NorthC's Almere data center (Rondebeltweg) that houses power infrastructure. No servers or data carriers caught fire, but the blaze burned part of the facility's power supply and the site lost power entirely — the compute survived, yet everything went dark, and NorthC ultimately had to rebuild the power plant with new transformers and UPS. (Published reporting says only that 'part of the power supply burnt down'; that BOTH the normal and standby feeds were lost is an engineering inference from the total, multi-day power loss and the full rebuild, not an official finding.) Because multiple Dutch organizations host critical systems there, the outage cascaded outward: Utrecht University, Statistics Netherlands (CBS), public-transport operator Transdev, a regional water board, research-ICT provider Surf, IBM Cloud's Amsterdam 03, and numerous GP practices all lost service. The fire was scaled down to GRIP 1 at 20:50 that evening and to GRIP 0 with the building partially released to NorthC teams at 00:35 on 8 May, kicking off a phased restoration estimated at up to 72 hours. Temporary redundant power and cooling were activated on 13 May, roughly a week after the fire. Grid power came back building-by-building over the following weeks, with Building 1's full utility-plus-standby topology targeted for 17 July 2026. The root cause remains officially undetermined; a draft cause report was only expected at end-September 2026 because the fire-damaged structure had to be secured first.
- Users affected
- Undisclosed headcount; multi-sector impact documented by named victims (Utrecht University, Statistics Netherlands/CBS, Transdev bus & tram, water board De Stichtse Rijnlanden, Surf, IBM Cloud AMS03, and GP/healthcare practices)
- Duration
- 6d 1h — Fire ~08:45 7 May → temporary power train for Almere 1 activated 09:30 13 May.
- Financial
- Not published; facility owner Keppel DC REIT stated the incident was not expected to have a material impact on FY2026 distribution per unit; no damages, insurance, or customer-loss figure disclosed
- Scope
- Sev-1 facility-level power loss (multi-day)
- Site
- NorthC Almere (Rondebeltweg) · Almere, Netherlands
- Services down
- Utrecht University network/applications/websites and access passes, Statistics Netherlands (CBS) platforms, Transdev bus and tram services, Water board Hoogheemraadschap De Stichtse Rijnlanden network, Surf member research/education infrastructure, IBM Cloud Amsterdam 03, GP practices' patient-record, scheduling and contact systems
How the defences failed
Blast radius is high because the failure reached across sectors of Dutch public life (higher education, national statistics, public transport, water management, healthcare, cloud) from a single site. Users and duration are high (multi-day facility power loss, weeks to full grid). Financial score is a mid-band estimate held down by the absence of any published damages figure and the owner's 'no material FY2026 DPU impact' statement; the true operational and tenant cost is undisclosed.
All 11 impact metrics
| Affected system class | Power infrastructure only — transformers + UPS destroyed, 0 IT devices fire-damaged |
| Facility electrical capacity | 11 MW |
| Facility footprint | ~26,000 sqm across two buildings (Almere 1 + Almere 2) |
| Fire outbreak time | ~08:45 (NorthC) / ~08:30 (Omroep Flevoland, TNW), Thu 7 May 2026 |
| Time to 'brand meester' (under control) | ~20:30 — approximately 11.5–12 hours of active firefighting |
| Casualties / injuries | 0 — all occupants evacuated in time; no dangerous-substance concentrations detected |
| Temporary power train | Activated 13 May 2026 (~6 days post-fire): generators + UPS + distribution units + >1 km of cable |
| Almere 2 grid reconnection | 29 May 2026 |
| Full site restoration target | Almere 1 phased — initial connection end June, full grid operation end July 2026 |
| Cause report timeline | DRAFT only by end September 2026 (~4.5 months after the fire) |
| Detection / suppression forensics | NOT DISCLOSED — no source reveals detection type/time or whether any active suppression discharged |
Sequence of events
- TRIGGER Fire breaks out at the rear technical room of the 'Almere 1' compartment on Rondebeltweg, Almere, where the technical facilities (emergency-power / technische ruimte) are located. NorthC dates it to 'around 08:45'; Omroep Flevoland and TNW report ~08:30.
- DETECTION Occupants alerted and the building evacuated in time — 'All people present were evacuated from the building in time' (CEO Alexandra Schless). NO source discloses the detection technology, zone or exact first-alarm time; only the human outcome (safe evacuation, no injuries) is documented.Safety officer
- MITIGATION Fire brigade responds and orders a COMPLETE datacenter shutdown; the fire is confirmed in the technical room of 'Almere 1'.Fire & rescue commander
- CASCADE In the undamaged half, backup generators start automatically — 'De noodstroomgeneratoren in het andere deel (Almere 2) sloegen automatisch aan.'
- MITIGATION Passive fire compartmentation confines the blaze to the rear compartment: 'The fire compartmentation prevented the smoke from spreading further' and 'smoke in the halls remained limited.' No active-suppression discharge is disclosed in any source.
- IMPACT Almere 1's power plant is lost: transformers and UPS destroyed; the emergency electrical installation is 'classified as lost.' No IT gear fire-damaged — damage concentrated around the site's power infrastructure.
- MITIGATION Veiligheidsregio Flevoland (at GRIP 2) issues an NL-Alert: avoid smoke, close windows/doors, switch off mechanical ventilation. Smoke drifts south toward 't Gooi; emergency measurements detect no dangerous-substance concentrations.Incident commander
- MITIGATION Firefighting hampered — the compartment is too unstable and too damaged to send crews inside. Facade sections are demolished with cranes for access; a drone from Brabant provides interior imaging; a fire truck from Lelystad Airport assists.Fire & rescue commander
- CASCADE Transdev loses contact with its regional control centre hosted at Almere; its servers 'had not been migrated to a backup location,' so bus-driver comms fail and the in-vehicle emergency button stops working.
- CASCADE Further downstream impact: Utrecht University research/education disrupted, Infomedics affected, local water board affected; SURF warns member institutions.
- MITIGATION Mayor Hein van der Loo characterises the scene as a 'vreselijke brand' / 'vuurzee' and warns the fire is not yet under control and may take a while.Authority / investigator
- MITIGATION 'Brand meester' (fire under control) reported — roughly 11–12 hours after outbreak.
- RECOVERY Incident downscaled from GRIP 2 to GRIP 1; NL-Alert withdrawn. (Precise clock time not independently re-verified this pass.)Incident commander
- RECOVERY Downscaled to GRIP 0; the building is partially released back to NorthC. (Precise clock time not independently re-verified this pass.)
- RECOVERY Temporary redundant power train activated for Almere 1 — generators, UPS, distribution units and more than 1 km of cable (~6 days after the fire; Computable reports 09:30). NorthC confirms 'temporary power May 13.'Service recovery lead
- RESTORED Almere 2 reconnected to the electricity grid.
- RESTORED Almere 1 restored to grid in phases as transformers and UPS are reinstalled — initial grid connection by end June, full grid operation targeted end July 2026.
- DETECTION Independent expert cause investigation proceeds only after the unstable structure is secured (demolition/investigation window 27 Jul–7 Aug); NorthC expects a DRAFT cause report by end September 2026 — ignition source and chemistry remain publicly unknown.
Response by role
What each role did
Roles the sequence of events shows acting; every entry quotes its source line. Select a time to jump to it.
Role by role
Recorded actions / playbook actions per role. A role with 0 recorded actions does not appear in the sources.
Whoever raised the alarm — detection and alarm time are not disclosed — Meets the first alarm: on-shift technician or security in a facility, on-call engineer in a service.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
Veiligheidsregio Flevoland ran the response at GRIP 2; no site commander is named — Owns every decision until formally relieved: site duty manager on scene, or the declared IC of a service incident.
On the record
- Veiligheidsregio Flevoland at GRIP 2 issues an NL-Alert: avoid smoke, close windows and doors, switch off ventilation
issues an NL-Alert: avoid smoke, close windows/doors, switch off mechanical ventilation
- Downscales to GRIP 1 at about 20:50 and withdraws the NL-Alert
Incident downscaled from GRIP 2 to GRIP 1
Playbook analyst guidance by failure mode, not a record of what happened
- FM-04Get a structural assessment early and keep crews out of the compartment when it cannot be entered safelyNIMS / ICS
- FM-02Keep staff and neighbours clear of the technical room and ask the region to issue smoke advice if the plume driftsNIMS / ICS
- FM-01Hand the fire brigade a briefing: what is in the room, what is still live, and where Almere 2 beginsNIMS / ICS
- FM-03Use the undamaged half: confirm Almere 2 generators are carrying load and keep Almere 1 de-energisedNFPA 110
- FM-07Check each facility action against the report when it lands, and record its statusNIMS / ICSCorrection of errors #5
Fire brigade, with a Brabant drone and a Lelystad Airport truck — External incident commander for fire, rescue and hazardous materials; works in unified command with the site.
On the record
- Orders a complete shutdown of the data center and confirms the fire in the Almere 1 technical room
Fire brigade responds and orders a COMPLETE datacenter shutdown
- Cannot send crews inside; demolishes facade sections and uses a drone for interior imaging
Facade sections are demolished with cranes for access
Playbook analyst guidance by failure mode, not a record of what happened
- FM-04Pre-plan structural-collapse access for power rooms: external attack points and pre-engineered crane or demolition accessNFPA 1561Improvement #5
- FM-02Plan for a long manual firefight where no suppression discharged, with cooling water on the compartment wallsNFPA 1561
- FM-01Order a complete shutdown of the data center before attacking the fireNFPA 1561
- FM-04Demolish facade sections by crane to attack from outside, and fly a drone for interior imagingNFPA 1561
NorthC staff who evacuated the building, per CEO Alexandra Schless — Head count, exclusion zones, PPE and the go / no-go for re-entry.
On the record
Playbook analyst guidance by failure mode, not a record of what happened
- FM-02Fit the technical room with automatic suppression sized for the equipment and any Li-ion battery, with aspirating detectionNFPA 75Improvement #6
NorthC power and facilities engineers — not named — Switching, isolation and lock-out of power sources, and safe re-energisation.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
NorthC teams that built the temporary power train — Restores customer service: failover, workload moves, capacity, backlog drain.
On the record
- Activates generators, UPS, distribution units and over 1 km of cable on 13 May, about six days on
Temporary redundant power train activated for Almere 1
Playbook analyst guidance by failure mode, not a record of what happened
- FM-05Connect Almere 2 to the grid first so its halls recover while Almere 1 is rebuiltCorrection of errors #3
- FM-06Bring tenant systems back in the order the tenants set, with their lifesaving functions firstISO 22301
- FM-01Run the independent cause investigation once the structure is safe, and fix the cause before re-energisingCorrection of errors #1
- FM-03Build a temporary redundant power train with generators, UPS, distribution and cableNFPA 110Correction of errors #2
- FM-05Reinstall transformers and UPS in phases and restore Almere 1 to gridCorrection of errors #4
- FM-04Secure the unstable structure first so the cause investigation can startISO 22301
NorthC status page; no named spokesperson in the sequence — Status page, customer notices, regulators and press; one voice, timed updates.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
- FM-02Publish the detection-to-alarm timeline and suppression status once the expert report allowsImprovement #1
Mayor Hein van der Loo and the Veiligheidsregio Flevoland — Regulator, investigator or court that establishes cause and obligations after the event.
On the record
- Mayor Hein van der Loo calls it a 'vreselijke brand' and warns it may take a while
warns the fire is not yet under control and may take a while
Playbook analyst guidance by failure mode, not a record of what happened
- FM-04Warn residents of smoke by NL-Alert while the fire burns, and withdraw it once measurements are clearNIMS / ICS
Transdev, Utrecht University, Infomedics, a water board and other tenants — The tenant or service user: their own redundancy, backups and continuity plan.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
- FM-06Fail over critical tenant systems, such as the control centre servers, to a second siteISO 22301Correction of errors #6
- FM-06Test failover of single-site dependencies on a schedule; a failed test is the warningISO 22301
- FM-06Switch to manual procedures for safety functions such as bus-driver radio and the emergency buttonISO 22301
- FM-03Move critical tenant systems to a second site and tell NorthC which loads are lifesavingISO 22301
- FM-07Ask NorthC in writing for the draft report and for the suppression and detection statusUptime OS
Failure mode & effects analysis (FMEA)
NorthC's Almere data center (two compartments, Almere 1 and Almere 2) from the fire in Almere 1's rear technical room through to grid reconnection: the power-plant equipment where the fire started, automatic detection and suppression in that room, the physical arrangement of Almere 1's primary and backup power, firefighting access to an unstable compartment, power restoration, the single-site tenant architectures that carried the impact outward, and the cause investigation. NorthC has published a running status log, not a post-mortem. The ignition source, equipment and chemistry are officially undetermined, with only a draft cause report expected at end-September 2026; detection technology, alarm time and any suppression discharge are undisclosed; and the loss of both primary and backup power is an engineering inference from the total multi-day outage and full rebuild, since press says only that 'part of the power supply burnt down'. Several timeline details are crawl-cited and not re-verified. The only completed actions (temporary power on 13 May, Almere 2 grid reconnection on 29 May) restore service rather than change the design, so no revised score is claimed: every mode is residual risk.
- Caught only after impactD ≥ 8
- 5 of 7
- Actions that cut occurrenceO lowered
- 0
- Actions that cut detectionD lowered
- 0
- Actions that cut severityblast radius unchanged
- 0
FM-06 Critical systems are hosted only at Almere with no failover to a second siteTenant single-site architectures (Transdev, Utrecht University, Infomedics, water board) 9·6·9 486 —
- Function
- Keep critical tenant systems running through the loss of one hosting facility
- Effect
- Transdev loses its regional control centre, bus-driver communications and the in-vehicle emergency button; Utrecht University, Infomedics and the water board lose service
- Cause
- Transdev's servers 'had not been migrated to a backup location'; other tenants carried single-facility dependencies
- Prevention in place
- None recorded on the tenant side
- Detection in place
- None; the dependency was revealed through the outage
- S 9
- Multi-sector outage of public services with no workaround, including loss of a safety function (the bus emergency button): the rubric's 9. Not 10 because no harm to a person is recorded.
- O 6
- Single-site hosting of critical systems is a standing, weakly guarded condition across several tenants: 'occasional'.
- D 9
- No tenant failover test is recorded; the dependency surfaced through the outage itself.
Corrective action
- Review and implement DR failover for single-site critical dependencies (tenant-side; open) Correction of errors #6
- Operator to advise or require single-site critical tenants to fail over to a second site (analyst recommendation) Improvement #4
Who acts — playbook
- Customer Fail over critical tenant systems, such as the control centre servers, to a second siteISO 22301Correction of errors #6
- Customer Test failover of single-site dependencies on a schedule; a failed test is the warningISO 22301
- Communications lead Tell tenants at the first hour that the site is down and give them an update timeITIL 4
- Customer Switch to manual procedures for safety functions such as bus-driver radio and the emergency buttonISO 22301
- Service recovery lead Bring tenant systems back in the order the tenants set, with their lifesaving functions firstISO 22301
Evidence
- Sequence of events #92026-05-07 daytime — Transdev loses contact with its regional control centre hosted at Almere; its servers 'had not been migrated to a backup location,' so bus-driver comms fail and the in-vehicle emergency button stops working.
- Sequence of events #102026-05-07 daytime — Further downstream impact: Utrecht University research/education disrupted, Infomedics affected, local water board affected; SURF warns member institutions.
- Contributing factor #4Customer-side single-site architecture with no DR failover (a downstream contributor to IMPACT, not to ignition): Transdev's regional control-centre servers 'had not been migrated to a backup location' (TNW, crawl-cited), collapsing bus-driver communications and the in-vehicle emergency button; Utrecht University, Infomedics and the local water board carried single-facility dependencies.
- Reference #7 · news“Transdev said its bus and tram services were also impacted”
- Reference #3 · press“Transdev's servers had not been migrated to a backup location”
FM-02 No source shows an automatic suppression system discharging or holding the fire; detection technology and first-alarm time are undisclosedAutomatic fire detection and suppression in the power room 8·6·8 384 —
- Function
- Detect a power-room fire early and suppress it before it destroys the power train
- Effect
- The fire burns for ~11-12 hours and is fought manually until 'brand meester' at ~20:30; the power train in the room is lost
- Cause
- Undetermined: suppression may have been absent, may have failed, or may be undisclosed
- Prevention in place
- Passive fire compartmentation, which kept smoke in the halls limited and IT undamaged
- Detection in place
- Undisclosed; only the outcome, timely evacuation, is documented
- S 8
- Sets how much of the power plant burned rather than whether the fire started; the facility loss is carried by FM-01, so this is scored at 8.
- O 6
- No active suppression is evidenced in a room full of power equipment, a weakly guarded condition: 'occasional'. Held at 6 because absence is undisclosed rather than proven.
- D 8
- Nothing in the record shows the suppression state was known before or during the fire; the gap shows only in the outcome.
Corrective action
- Publish the detection-to-alarm timeline and automatic-suppression status for the power room (open / not disclosed) Correction of errors #5
- Confirm UPS battery chemistry and, if Li-ion, fit off-gas/aspirating detection and runaway-rated suppression (analyst recommendation) Improvement #6
Who acts — playbook
- Safety officer Fit the technical room with automatic suppression sized for the equipment and any Li-ion battery, with aspirating detectionNFPA 75Improvement #6
- Communications lead Publish the detection-to-alarm timeline and suppression status once the expert report allowsImprovement #1
- First responder Log the time of the first alarm and the call to the fire brigadeNFPA 72
- Fire & rescue commander Plan for a long manual firefight where no suppression discharged, with cooling water on the compartment wallsNFPA 1561
- Incident commander Keep staff and neighbours clear of the technical room and ask the region to issue smoke advice if the plume driftsNIMS / ICS
- Authorised electrical person Do not re-energise anything in the compartment until suppression state is recorded and repairedNFPA 75
On the record at this failure
Evidence
- Contributing factor #2Absence (or non-disclosure) of effective automatic suppression in the affected power room: no source evidences that any gaseous / water-mist / sprinkler system discharged or held the fire, which burned ~11–12 hours and required manual firefighting until 'brand meester' at ~20:30 (Omroep Flevoland, crawl-cited). Whether a suppression system existed and failed, or was never installed, is an open gap.
- Metric #11Detection / suppression forensics: NOT DISCLOSED — no source reveals detection type/time or whether any active suppression discharged
- Sequence of events #22026-05-07 ~08:30–08:45 — Occupants alerted and the building evacuated in time — 'All people present were evacuated from the building in time' (CEO Alexandra Schless). NO source discloses the detection technology, zone or exact first-alarm time; only the human outcome (safe evacuation, no injuries) is documented.
- Metric #5Time to 'brand meester' (under control): ~20:30 — approximately 11.5–12 hours of active firefighting
- Sequence of events #5“No active-suppression discharge is disclosed in any source.”
FM-01 A fire breaks out in the emergency-power technical room from an undetermined sourcePower-plant equipment in Almere 1's rear technical room 10·4·9 360 —
- Function
- Convert and condition power for the site without becoming an ignition source
- Effect
- Transformers and UPS destroyed and the emergency electrical installation 'classified as lost'; the whole data center is shut down; an NL-Alert warns residents about smoke; all occupants evacuated in time with no injuries
- Cause
- Undetermined. The dossier names two physically plausible families, a UPS battery thermal event or an electrical fault in a transformer or switchgear, and asserts neither; no maintenance or testing lapse is evidenced or ruled out
- Prevention in place
- None recorded; maintenance, inspection and testing history unpublished
- Detection in place
- None recorded for the equipment before the fire
- S 10
- Rubric 10, loss of the facility: the power plant was destroyed, the whole site went dark for days, and the compartment had to be partly demolished. People were put at risk (evacuation, public smoke alert), though none were hurt.
- O 4
- With the cause unknown and no lapse evidenced, the dossier supports only 'infrequent'; it cannot support a higher or lower score.
- D 9
- No condition monitoring of the equipment that ignited is recorded; held at 9 rather than 10 because the monitoring regime is undisclosed, not shown to be absent.
Corrective action
- Independent expert cause investigation (in progress; draft report expected end September 2026) Correction of errors #1
- Independent IR/thermographic inspection of transformers, switchgear and UPS plus battery-string monitoring (analyst recommendation) Improvement #3
Who acts — playbook
- Authorised electrical person Run thermographic inspection of transformers, switchgear and UPS on a fixed cadence, and monitor battery-string temperature continuouslyNFPA 70EImprovement #3
- First responder Treat the first alarm from the technical room as a real fire: evacuate first and call the fire brigade before anyone goes to lookNFPA 72
- Incident commander Hand the fire brigade a briefing: what is in the room, what is still live, and where Almere 2 beginsNIMS / ICS
- Authorised electrical person Isolate Almere 1 power feeds and let Almere 2 generators carry the undamaged halfNFPA 110
- Fire & rescue commander Order a complete shutdown of the data center before attacking the fireNFPA 1561
- Service recovery lead Run the independent cause investigation once the structure is safe, and fix the cause before re-energisingCorrection of errors #1
On the record at this failure
- Incident commander Veiligheidsregio Flevoland at GRIP 2 issues an NL-Alert: avoid smoke, close windows and doors, switch off ventilation
Evidence
- Sequence of events #12026-05-07 ~08:30–08:45 — Fire breaks out at the rear technical room of the 'Almere 1' compartment on Rondebeltweg, Almere, where the technical facilities (emergency-power / technische ruimte) are located. NorthC dates it to 'around 08:45'; Omroep Flevoland and TNW report ~08:30.
- Sequence of events #62026-05-07 ~09:00+ — Almere 1's power plant is lost: transformers and UPS destroyed; the emergency electrical installation is 'classified as lost.' No IT gear fire-damaged — damage concentrated around the site's power infrastructure.
- Metric #1Affected system class: Power infrastructure only — transformers + UPS destroyed, 0 IT devices fire-damaged
- Metric #6Casualties / injuries: 0 — all occupants evacuated in time; no dangerous-substance concentrations detected
- Sequence of events #72026-05-07 daytime — Veiligheidsregio Flevoland (at GRIP 2) issues an NL-Alert: avoid smoke, close windows/doors, switch off mechanical ventilation. Smoke drifts south toward 't Gooi; emergency measurements detect no dangerous-substance concentrations.
- Root cause“BOTH are UNCONFIRMED; no source attributes ignition to either, and this dossier asserts neither”
FM-03 Primary and backup power elements share one fire compartment, so a single fire destroys transformers and UPS togetherAlmere 1 power train (transformers and UPS in one technical room) 9·4·9 324 —
- Function
- Keep Almere 1 powered through the loss of any one power-train element
- Effect
- Almere 1's entire emergency electrical installation is lost; the site is without power until a temporary train is activated about six days later; Utrecht University, CBS, Transdev, a water board, Surf, IBM Cloud AMS03 and GP practices lose service
- Cause
- Insufficient physical separation between redundant power-train elements inside Almere 1 (the dossier's latent-root analysis; loss of both feeds is an inference, not an official finding)
- Prevention in place
- Separation between Almere 1 and Almere 2, which held
- Detection in place
- None before the incident; the shared exposure was revealed by the fire
- S 9
- Facility-wide, multi-day outage for every tenant, with no workaround for single-site customers: the rubric's 9. Not 10 because the people hazard and the physical destruction are carried by FM-01.
- O 4
- A standing design condition that only bites when a fire starts in that room: 'infrequent'.
- D 9
- No review or test is recorded that exposed the shared fire exposure of primary and backup power; it was found through impact.
Corrective action
- Place redundant power-train elements in distinct fire compartments (analyst recommendation) Improvement #2
- Rebuild Almere 1's emergency electrical installation and restore to grid (phased; the dossier does not say the rebuild separates the elements) Correction of errors #4
Who acts — playbook
- Authorised electrical person Put transformers, UPS and switchgear of each compartment in separate fire compartmentsNFPA 75Improvement #2
- Authorised electrical person Map which loads share which power room, so one fire's reach is known beforehandUptime OSLesson #2
- Incident commander Use the undamaged half: confirm Almere 2 generators are carrying load and keep Almere 1 de-energisedNFPA 110
- Customer Move critical tenant systems to a second site and tell NorthC which loads are lifesavingISO 22301
- Service recovery lead Build a temporary redundant power train with generators, UPS, distribution and cableNFPA 110Correction of errors #2
- Communications lead Publish each reconnection milestone on the status page, with date and which hallITIL 4
Evidence
- Contributing factor #1Co-location of primary and backup power in one room (Almere 1): a single fire in the rear technical room destroyed transformers AND UPS together, so the entire emergency electrical installation of that compartment was 'classified as lost' (NorthC, verified) — indicating insufficient physical separation between the power train's redundant elements within Almere 1.
- Root cause“a single fire destroyed the entire emergency electrical installation of that half of the site”
- Reference #6 · press“took down both primary and backup power systems”
- Reference #8 · news“part of the power supply burnt down”
- Sequence of events #42026-05-07 morning — In the undamaged half, backup generators start automatically — 'De noodstroomgeneratoren in het andere deel (Almere 2) sloegen automatisch aan.'
FM-07 Ignition source, chemistry, detection timeline and suppression status remain undisclosed, with only a draft cause report due ~4.5 months after the fireCause investigation and disclosure 3·8·9 216 —
- Function
- Establish and publish the ignition cause and the performance of detection and suppression
- Effect
- Tenants cannot judge whether the rebuilt site carries the same exposure; no maintenance lapse can be confirmed or excluded
- Cause
- Forensics gated on securing an unstable structure; NorthC has not published detection or suppression details
- Prevention in place
- None recorded
- Detection in place
- Visible only as the absence of a report
- S 3
- Affects verification and trust rather than any running service: 'internal impact only'.
- O 8
- Every forensic detail the dossier lists is undisclosed, so the gap is the routine state of the record: 'frequent'. Part of the delay is defensible (structural safety); the detection and suppression silence is not tied to it.
- D 9
- Nothing surfaces it except its absence.
Corrective action
- Independent expert cause investigation (in progress) Correction of errors #1
- Publish detection and suppression status (open / not disclosed) Correction of errors #5
- Once the expert report permits, publish whether automatic suppression existed in the power room, discharged and held (analyst recommendation) Improvement #1
Who acts — playbook
- Service recovery lead Commit to a draft cause report date and publish the findings, including maintenance, hot-work and test historyISO 22301Improvement #3
- Authorised electrical person Preserve the damaged equipment and the maintenance logs for the investigatorsNFPA 70E
- Communications lead State what is known and not known about ignition source and chemistry; do not speculateITIL 4Lesson #5
- Customer Ask NorthC in writing for the draft report and for the suppression and detection statusUptime OS
- Incident commander Check each facility action against the report when it lands, and record its statusNIMS / ICSCorrection of errors #5
Evidence
- Metric #10Cause report timeline: DRAFT only by end September 2026 (~4.5 months after the fire)
- Contributing factor #5Maintenance / inspection / testing status is UNEVIDENCED, not exonerated: with the cause investigation open and only a draft report due end September 2026 (NorthC, verified), no maintenance, hot-work, or testing lapse has been disclosed or ruled out — the factor cannot be assessed from the public record.
- Correction of errors #5Publish detection-to-alarm timeline and automatic-suppression status for the affected power room (Open / not disclosed)
- Root cause“any specific attribution would be fabrication”
FM-05 Restoration needs a temporary power train built from scratch and weeks of transformer and UPS reinstallationPower restoration after loss of the power plant 7·4·6 168 —
- Function
- Restore power to the data halls quickly once the fire is out and the building is released
- Effect
- Temporary power on 13 May (~6 days post-fire); Almere 2 back on grid 29 May; Almere 1 restored in phases into July
- Cause
- The emergency electrical installation was destroyed, so there was no surviving plant to switch to
- Prevention in place
- Backup generators in Almere 2 started automatically
- Detection in place
- Known from the moment the building was released
- S 7
- Sets the six-day duration of the outage that FM-03 causes; scored at 7 so the same outage is not counted twice at full weight.
- O 4
- Follows only from total loss of a compartment's power plant: 'infrequent'.
- D 6
- The need was clear at onset, but no pre-staged temporary power is recorded: 'detected at onset, not prevented'.
Corrective action
- Temporary redundant power train for Almere 1 (completed 13 May 2026; recovery for this event, not a design change) Correction of errors #2
- Reconnect Almere 2 to the grid (completed 29 May 2026) Correction of errors #3
Who acts — playbook
- Service recovery lead Hold a plan and pre-contracted supply for a temporary power train, so it is not designed during the outageNIST SP 800-34
- Authorised electrical person Inventory the plant lost and the surviving plant the day the building is releasedISO 22301
- Service recovery lead Connect Almere 2 to the grid first so its halls recover while Almere 1 is rebuiltCorrection of errors #3
- Service recovery lead Reinstall transformers and UPS in phases and restore Almere 1 to gridCorrection of errors #4
- Communications lead Give tenants dated power milestones and hold to themITIL 4
On the record at this failure
- Service recovery lead Activates generators, UPS, distribution units and over 1 km of cable on 13 May, about six days on
Evidence
- Sequence of events #152026-05-13 — Temporary redundant power train activated for Almere 1 — generators, UPS, distribution units and more than 1 km of cable (~6 days after the fire; Computable reports 09:30). NorthC confirms 'temporary power May 13.'
- Metric #7Temporary power train: Activated 13 May 2026 (~6 days post-fire): generators + UPS + distribution units + >1 km of cable
- Sequence of events #162026-05-29 — Almere 2 reconnected to the electricity grid.
- Sequence of events #172026-06 to 2026-07 — Almere 1 restored to grid in phases as transformers and UPS are reinstalled — initial grid connection by end June, full grid operation targeted end July 2026.
- Reference #1 · official-postmortem“On 17 July, the data center will be fully reconnected to the regular grid”
FM-04 The compartment becomes too unstable and damaged to enter, so crews must demolish facade sections with cranes and use a drone for interior imagingFirefighting access to the burning compartment 6·4·6 144 —
- Function
- Let crews reach and extinguish a power-room fire quickly
- Effect
- Active firefighting lasts ~11.5-12 hours; the cause investigation cannot start until the structure is secured in a 27 July-7 August window
- Cause
- Structural fragility of the burning compartment
- Prevention in place
- External support: crane demolition, a drone from Brabant, a fire truck from Lelystad Airport
- Detection in place
- Known to responders on scene
- S 6
- Extends the fire and delays the investigation rather than adding new service loss; scored at 6 because the outage itself is carried by FM-01 and FM-03.
- O 4
- Needs a fire intense enough to compromise the structure: 'infrequent'.
- D 6
- Responders recognised the instability at once but could not avoid it: 'detected at onset, not prevented'.
Corrective action
- Pre-plan structural-collapse firefighting access for power rooms (analyst recommendation) Improvement #5
Who acts — playbook
- Fire & rescue commander Pre-plan structural-collapse access for power rooms: external attack points and pre-engineered crane or demolition accessNFPA 1561Improvement #5
- Incident commander Get a structural assessment early and keep crews out of the compartment when it cannot be entered safelyNIMS / ICS
- Fire & rescue commander Demolish facade sections by crane to attack from outside, and fly a drone for interior imagingNFPA 1561
- Authority / investigator Warn residents of smoke by NL-Alert while the fire burns, and withdraw it once measurements are clearNIMS / ICS
- Service recovery lead Secure the unstable structure first so the cause investigation can startISO 22301
On the record at this failure
- Fire & rescue commander Cannot send crews inside; demolishes facade sections and uses a drone for interior imaging
Evidence
- Sequence of events #82026-05-07 daytime — Firefighting hampered — the compartment is too unstable and too damaged to send crews inside. Facade sections are demolished with cranes for access; a drone from Brabant provides interior imaging; a fire truck from Lelystad Airport assists.
- Contributing factor #3Structural fragility of the burning compartment slowed both firefighting and forensics: the room was too unstable and too damaged to send crews inside, forcing crane demolition of the facade and drone imaging (Omroep Flevoland, crawl-cited) — extending outage duration and pushing the cause investigation to a 27 July–7 August 2026 demolition/investigation window (NorthC, verified).
- Sequence of events #182026-07-27 to 2026-09 (end) — Independent expert cause investigation proceeds only after the unstable structure is secured (demolition/investigation window 27 Jul–7 Aug); NorthC expects a DRAFT cause report by end September 2026 — ignition source and chemistry remain publicly unknown.
- Sequence of events #122026-05-07 ~20:30 — 'Brand meester' (fire under control) reported — roughly 11–12 hours after outbreak.
Scoring rubric and method
Scales adapted from IEC 60812:2018 and AIAG-VDA. RPN = S × O × D. High: S ≥ 9 with O ≥ 4 or D ≥ 7, or RPN ≥ 300. Medium: RPN ≥ 120 or S ≥ 7. Severity overrides the product: 9 × 2 × 9 = 162 would otherwise hide a region-wide outage nothing could catch. Quotes are checked verbatim against this dossier; a revised score needs a published action. RZ analyst assessment, not an operator document.
Severity
| 10 | Hazard to people, or loss of the facility / several regions |
| 9 | Region-wide or provider-wide outage of a foundational service, no workaround |
| 8 | Full outage of a major service for hours |
| 7 | Major degradation of a major service |
| 6 | Partial outage confined to one zone or one service |
| 5 | Customer-visible degradation |
| 4 | Limited customer impact |
| 3 | Internal impact only |
| 2 | Negligible |
| 1 | No effect |
Occurrence
| 10 | Near certain: the cause is present in normal operation |
| 8 | Frequent: routine work exercises the cause |
| 6 | Occasional: a foreseeable slip or condition, weakly guarded |
| 4 | Infrequent: needs an unusual combination |
| 2 | Remote: guarded by design |
| 1 | Eliminated by design |
Detection
| 10 | No control could detect it |
| 9 | Detected only through customer impact |
| 8 | Detected after impact by internal monitoring |
| 6 | Detected at onset, not prevented |
| 4 | Detected before impact with time to act |
| 2 | Automated interlock almost certainly stops it |
| 1 | Certain to be stopped |
Root cause and contributing factors
Full root-cause narrative
Contributing factors by category
- Co-location of primary and backup power in one room (Almere 1): a single fire in the rear technical room destroyed transformers AND UPS together, so the entire emergency electrical installation of that compartment was 'classified as lost' (NorthC, verified) — indicating insufficient physical separation between the power train's redundant elements within Almere 1.
- Absence (or non-disclosure) of effective automatic suppression in the affected power room: no source evidences that any gaseous / water-mist / sprinkler system discharged or held the fire, which burned ~11–12 hours and required manual firefighting until 'brand meester' at ~20:30 (Omroep Flevoland, crawl-cited). Whether a suppression system existed and failed, or was never installed, is an open gap.
- Structural fragility of the burning compartment slowed both firefighting and forensics: the room was too unstable and too damaged to send crews inside, forcing crane demolition of the facade and drone imaging (Omroep Flevoland, crawl-cited) — extending outage duration and pushing the cause investigation to a 27 July–7 August 2026 demolition/investigation window (NorthC, verified).
- Customer-side single-site architecture with no DR failover (a downstream contributor to IMPACT, not to ignition): Transdev's regional control-centre servers 'had not been migrated to a backup location' (TNW, crawl-cited), collapsing bus-driver communications and the in-vehicle emergency button; Utrecht University, Infomedics and the local water board carried single-facility dependencies.
- Maintenance / inspection / testing status is UNEVIDENCED, not exonerated: with the cause investigation open and only a draft report due end September 2026 (NorthC, verified), no maintenance, hot-work, or testing lapse has been disclosed or ruled out — the factor cannot be assessed from the public record.
Analysis
What happened
At ~08:30–08:45 on 7 May 2026 a fire broke out in the rear technical room of the 'Almere 1' compartment of NorthC's Almere data center, centred on the site's power infrastructure. Everyone was evacuated in time with no injuries. Transformers and UPS in that room were destroyed and the emergency electrical installation was 'classified as lost' (NorthC, verified). The fire brigade ordered a full shutdown and fought the blaze into the evening, with 'brand meester' reported around 20:30. The ignition source and chemistry remain publicly unknown; NorthC expects only a draft cause report by end September 2026.
Why the data halls survived: passive containment
The load-bearing safety story is passive fire compartmentation, not active suppression. Per NorthC, 'The fire compartmentation prevented the smoke from spreading further' and 'smoke in the halls remained limited.' The two-compartment topology held between Almere 1 and Almere 2, so no IT gear was fire-damaged even as the Almere 1 power room was destroyed. No source discloses whether any automatic suppression existed in that room or discharged — a genuine gap given an ~11–12 hour manual firefight.
The real single point of failure: a co-located power train
Inter-compartment separation worked, but within Almere 1 the primary and backup power shared one technical room closely enough that a single fire destroyed transformers and UPS together — the entire emergency electrical installation of that half of the site. This is the central latent root: redundancy defined by device counts (N+1) rather than physical fire separation collapses to a single point of failure when both elements sit in one space. Rebuild and future design should place redundant power-train elements in distinct fire compartments.
Downstream impact was a customer-architecture failure, not a NorthC fire-safety failure
The most visible real-world harm came from single-site tenant architectures. Transdev's regional control-centre servers 'had not been migrated to a backup location' (TNW, crawl-cited), so bus-driver communications and the in-vehicle emergency button failed. Utrecht University, Infomedics and the local water board carried single-facility dependencies. Utrecht University's reported damages claim targets its telecom provider KPN, not a NorthC maintenance breach — underscoring that DR failover is a tenant responsibility the operator should actively encourage.
What remains unknown — and why that is defensible
Three things are genuinely undisclosed: (1) the ignition source/equipment/chemistry, (2) the detection technology and first-alarm time, and (3) whether any automatic suppression existed or discharged. The cause gap is defensible: forensics could only start after an unstable structure was secured (27 Jul–7 Aug window), so a draft report ~4.5 months out is realistic. The detection/suppression gaps are less defensible as disclosure and should be closed once safe. No maintenance, hot-work, or testing lapse is evidenced — but with the investigation open, none is ruled out either.
Technical deep-dive
Corrective actions and lessons
Correction of errors
| Action | Owner | Status |
|---|---|---|
| Independent expert cause investigation (ignition source, chemistry, mechanism) | NorthC + independent experts | In progress — investigation/demolition window 27 Jul–7 Aug 2026; DRAFT report expected end September 2026 |
| Activate temporary redundant power train for Almere 1 (generators, UPS, distribution, >1 km cable) | NorthC | Completed 13 May 2026 |
| Reconnect Almere 2 to the electricity grid | NorthC | Completed 29 May 2026 |
| Rebuild Almere 1 emergency electrical installation (reinstall transformers + UPS) and restore to grid | NorthC | Phased — initial grid connection end June; full grid operation targeted end July 2026 |
| Publish detection-to-alarm timeline and automatic-suppression status for the affected power room | NorthC | Open / not disclosed |
| Review and implement DR failover for single-site critical dependencies | Tenants (Transdev, Utrecht University, Infomedics, water board) | Tenant-side — open; Utrecht University damages claim reportedly directed at KPN, not NorthC |
Lessons learnt
- Passive compartmentation is the hero of this incident — it confined an intense power-room fire and kept the data halls and IT largely intact with no injuries; sustained investment in passive fire separation pays off exactly when active systems are absent or unknown.
- Redundancy that shares a room is not redundancy — co-locating transformers and UPS in one technical space meant a single fire took out an entire compartment's power train; physical separation, not just N+1 counts, defines real resilience.
- Facility resilience does not equal customer resilience — the worst real-world harm (bus comms and the in-vehicle emergency button failing) fell on a tenant that had not replicated to a backup site; operators should actively push single-site critical customers toward DR.
- Cause timelines stretch to months when the structure is unsafe — forensics were gated by a demolition window, so a draft cause report only ~4.5 months out is a realistic expectation, not negligence; set stakeholder expectations accordingly.
- Silence on detection and suppression erodes trust — the absence of any public detail on fire detection or automatic suppression is itself a finding; transparent post-incident disclosure (once safe) is part of operational credibility.
Improvements
- Safety (disclosure): once the expert report permits, publish the detection-to-alarm timeline and whether any automatic suppression existed in the power room, discharged, and held — the ~11–12 h manual firefight and total silence on active suppression are the single largest unexplained safety gaps in the public record.
- Design (separation): physically separate the redundant elements of each compartment's power train (transformers, UPS/battery, switchgear) into distinct fire compartments so a single fire cannot destroy both primary and backup power for one hall, as happened in Almere 1.
- Maintenance (assurance): once the cause report lands, publish the technical room's maintenance, inspection, hot-work and testing history; institute an independent thermographic/IR inspection cadence on transformers, switchgear and UPS, plus continuous battery-string health/temperature monitoring for early thermal-runaway detection.
- Customer resilience: advise/require single-site critical tenants (mobility, health, utilities such as Transdev, Utrecht University, Infomedics, the water board) to implement DR failover to a second site, since facility resilience did not prevent tenant outages.
- Emergency response: pre-plan structural-collapse firefighting access for power rooms (external attack points, pre-engineered crane/demolition access) so a compartment that becomes too unstable to enter does not extend the outage by ~11–12 hours.
- Battery chemistry: confirm and disclose the UPS battery chemistry (VRLA vs Li-ion) and, where Li-ion, deploy off-gassing/aspirating detection and battery-room-rated suppression sized for thermal runaway.
References and provenance
- official-postmortem Fire in our data center in Almere (running update log)“On 17 July, the data center will be fully reconnected to the regular grid, with the emergency generators as back-up.”https://www.northcdatacenters.com/en/news/fire-in-our-data-center-in-almere/
- press DataCenterDynamics — NorthC datacenter catches fire in Almere, Netherlands“Damage was concentrated around the site's power infrastructure; no IT gear was damaged by fire (11 MW / ~26,000 sqm, two buildings).”https://www.datacenterdynamics.com/en/news/
- press The Next Web (TNW) — Fire at Dutch data center NorthC Almere“Transdev's servers had not been migrated to a backup location, so bus-driver communications and the in-vehicle emergency button stopped working.”https://thenextweb.com/
- press Computable — NorthC Almere datacenter fire and recovery“De noodstroomgeneratoren in het andere deel (Almere 2) sloegen automatisch aan.”https://www.computable.nl/
- press Omroep Flevoland — Grote brand datacenter Almere“'Brand meester' was reported around 20:30, roughly 11–12 hours after outbreak; the compartment was too unstable to enter, requiring crane demolition and drone imaging.”https://www.omroepflevoland.nl/
- press Major fire takes down NorthC data centre in the Netherlands for six days — Structure Research“NorthC Datacenters had a fire at its facility in Almere near Amsterdam on May 7 which took down both primary and backup power systems.”https://structureresearch.net/2026/05/20/major-fire-takes-down-northc-data-centre-in-the-netherlands-for-six-days/
- news NorthC data center outside Amsterdam suffers fire“Transdev said its bus and tram services were also impacted ... IBM Cloud has also reported issues at the data center hosting its Amsterdam 03 facility.”https://www.datacenterdynamics.com/en/news/northc-data-center-outside-amsterdam-suffers-fire/
- news Almere data center fire under control; caused outages throughout Netherlands“No servers or data carriers caught fire, but part of the power supply burnt down.”https://nltimes.nl/2026/05/08/almere-data-center-fire-control-caused-outages-throughout-netherlands
- news Major fire takes down NorthC data centre for six days“Major fire takes down NorthC data centre in the Netherlands for six days.”https://www.structureresearch.net/2026/05/20/major-fire-takes-down-northc-data-centre-in-the-netherlands-for-six-days/
- news Fire at NorthC data center: all personnel evacuated in time“At the time of writing, it was unclear how many companies experienced technical issues as a result of the fire.”https://www.techzine.eu/news/infrastructure/141131/fire-at-northc-data-center-all-personnel-evacuated-in-time/
Quotes are short, attributed, and for provenance only; the analysis is original. Last verified 2026-08-01.