Red Sea Subsea Cable Cuts — Rubymar Anchor Severs AAE-1, Seacom/TGN-EA and EIG off Yemen
Summary
On 24 February 2024 three submarine cable systems — Seacom (which Kentik groups with TGN-EA), AAE-1 and EIG — were severed off the west coast of Yemen in the Red Sea. The generally-accepted cause is the anchor of the MV Rubymar, an abandoned cargo ship struck by Houthi forces on 18 February, dragging across the cable corridor after the anchor was dropped when the vessel came under fire. The cuts degraded a large share of Asia-Europe-Middle-East transit (commonly cited at ~25%, though that figure is unattributed in reachable sources) and were felt across East Africa and the Middle East. Physical repair did not begin until July 2024, when an E-Marine cable ship restored AAE-1 first and then the remaining two cables. The cause is the accepted narrative rather than a forensic consortium finding; TGN-EA is named alongside Seacom by Kentik, but whether it is a physically distinct 4th cable or shares the Seacom system remains only partly corroborated.
- Users affected
- Reported as tens of millions across East Africa and the Middle East in the seed brief, but UNCORROBORATED — no reachable source provides an absolute affected-user count; documented impact is country-level connectivity degradation plus one operator's earnings hit.
- Duration
- Cables cut 24 Feb 2024; AAE-1 repaired 'July 2024', no day given; end-user traffic loss ~0.
- Financial
- Not disclosed in absolute terms. Only quantified figure: Seacom's contribution to 30%-shareholder Remgro's headline earnings fell to ~R2M from ~R32M the prior year (~R30M / ~94% drop), attributed mainly to once-off cable-repair costs. Absolute repair spend never published.
- Scope
- Major regional connectivity incident — multi-cable, multi-country, ~5-month restoration
- Site
- Red Sea cable corridor (Bab-el-Mandeb / off west coast of Yemen) · Bab-el-Mandeb, Yemen
- Services down
- Seacom submarine cable (Kentik lists the damaged system as 'Seacom/TGN-EA'), AAE-1 (Asia-Africa-Europe-1), EIG (Europe India Gateway), ~25% of Asia-Europe / Asia-Middle-East transit capacity degraded (screening estimate, unattributed)
How the defences failed
Blast radius and duration dominate: multiple international backbones down for roughly five months across a chokepoint carrying a large share of Asia-Europe traffic. User score is provisional — the 'tens of millions' figure is uncorroborated. Financial score is low because only one operator's ~R30M earnings delta is documented; the absolute repair bill and wider economic cost were never disclosed.
All 11 impact metrics
| Subsea cable systems severed | 3 (Seacom/Tata TGN-Eurasia, AAE-1, EIG); HGC reportedly cited 4 |
| Asia-Europe / Red Sea capacity lost | ~25% ('a quarter') |
| End-user traffic loss observed (Feb 22-28) | ~0 (no material loss across affected East-African markets) |
| Vessel drift distance while not under command | >70 km (43 mi) by 26 Feb 2024 |
| Anti-ship missiles fired at Rubymar | 2 (one struck) |
| Crew evacuated | 24, by container ship Lobivia |
| Restoration time (AAE-1) | ~4-5 months (pending 13 May 2024 -> completed July 2024) |
| Detection date of cable damage | 24 Feb 2024 (Cloudflare); exact UTC not published |
| Industry baseline: faults from anchors/fishing | ~70-80% of all cable faults |
| Vessel profile | ~171 m bulk carrier, built 1997; fertiliser cargo (press/CENTCOM: ~21,000 t ammonium-phosphate-sulphate) |
| Fault-water depth regime | shallow Bab-el-Mandeb corridor where dragged anchors hook armoured cable |
Sequence of events
- TRIGGER Houthi forces fire two anti-ship missiles at MV Rubymar off Yemen; one strikes, severely damaging and disabling the Belize-flagged, Lebanese-operated (GMZ) bulk carrier (~171 m, built 1997, Marshall Is.-registered owner).
- TRIGGER All 24 crew evacuated by the container ship Lobivia; the disabled, not-under-command vessel is left adrift with its anchor down.Safety officer
- CASCADE Unmanned vessel 'moved more than 70 kilometres (43 mi) while not under command', dragging its anchor across the Bab-el-Mandeb seabed cable corridor.
- IMPACT Under the leading hypothesis the dragging anchor shears three armoured subsea systems — Seacom/Tata TGN-Eurasia, AAE-1 and EIG; Wikipedia calls it 'One hypothesis' and the cause 'currently unknown'.
- DETECTION Optical continuity lost; operators' line-monitoring/OTDR systems register faults at measured distances; Cloudflare Radar dates the cable damage to 24 Feb 2024 and names the three systems.
- DETECTION Loss observed out-of-band via BGP routing changes, latency and traffic monitoring by Kentik (Doug Madory), Cloudflare Radar and NetBlocks — no facility alarm involved.First responder
- DETECTION Cloudflare: 'no loss of traffic was observed across these countries in Cloudflare Radar' (Tanzania, Kenya, Uganda, Mozambique) — fault visible on capacity/routing telemetry while end-user traffic stayed up.
- MITIGATION Operator HGC reported rerouting affected traffic onto surviving cables and terrestrial paths (protection switching, not suppression).Operations lead
- MITIGATION Affected wavelengths dropped and re-groomed onto surviving fibres and parallel/terrestrial routes — optical-layer isolation of the severed segments.Operations lead
- IMPACT Roughly a quarter (~25%) of Red Sea / Europe-Asia-Middle East capacity lost; Wikipedia states the damage 'affected 25% of the internet traffic between Europe, Asia and the Middle East'.
- IMPACT Despite the capacity loss, Cloudflare telemetry shows little-to-no end-user traffic loss — parallel and terrestrial diversity absorbed the load.
- CASCADE MV Rubymar sinks, ending the drift.
- RECOVERY Repair-ship dispatch gated by war-risk: active missile/drone threat, war-risk insurance and naval-security constraints delay intervention for months.
- RECOVERY AAE-1 repairs still 'pending due to the refusal of permits from the Yemeni Government'.Authority / investigator
- RESTORED 'In July 2024, repairs were successfully carried out on the AAE-1 cable' — an ~4-5 month restoration versus the days-to-weeks typical in a permissive environment.Service recovery lead
- RESTORED No consortium- or regulator-issued root-cause report published; cause officially 'currently unknown' — the record remains telemetry-vendor analysis plus press.
Response by role
What each role did
Roles the sequence of events shows acting; every entry quotes its source line. Select a time to jump to it.
Role by role
Recorded actions / playbook actions per role. A role with 0 recorded actions does not appear in the sources.
Cable operators' line-monitoring teams, plus outside observers Kentik, Cloudflare Radar and NetBlocks — Meets the first alarm: on-shift technician or security in a facility, on-call engineer in a service.
On the record
- Spot the loss from routing, latency and traffic data, not from any facility alarm
Loss observed out-of-band via BGP routing changes, latency and traffic monitoring by Kentik (Doug Madory), Cloudflare Radar and NetBlocks
Playbook analyst guidance by failure mode, not a record of what happened
- FM-04Start the permit request on the day of the cut and log the date each refusal arrivesITIL 4
- FM-01Watch AIS for any vessel stopped or drifting inside the cable corridor and alert the owners' NOC at onceSRE incident mgmtImprovement #2
- FM-05Check the repair ship's position, insurance cover and spares inventory against the region quarterlyISO 22301
- FM-02Map each system's physical route against the others and flag every shared corridor in the carrier risk registerISO 22301
- FM-06Log the OTDR distance and time for every break at the moment of detection, to support later attributionITIL 4
- FM-03Trend utilisation on surviving cables and terrestrial paths and alert when it passes a set headroom levelSRE incident mgmt
No incident commander is named in the record — Owns every decision until formally relieved: site duty manager on scene, or the declared IC of a service incident.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
- FM-04Escalate the refused permit to governments and the UN through the consortium, not through the ship operatorITIL 4
- FM-05Decide at once whether to wait for the security situation or send the ship with escortNIMS / ICS
- FM-02At the first cut, check which other systems share the corridor and treat them as at riskSRE incident mgmt
- FM-03Hold maintenance on the surviving paths during the outageChange management
- FM-06Issue the consortium's findings so the cause stops being only 'generally accepted'ITIL 4
Operators such as HGC who rerouted traffic and re-groomed wavelengths — Technical lead who diagnoses and drives the fix; the subject-matter expert at the keyboard or the switchboard.
On the record
- HGC moves affected traffic onto surviving cables and terrestrial paths
Operator HGC reported rerouting affected traffic onto surviving cables and terrestrial paths
- Operators drop and re-groom wavelengths onto surviving fibres and parallel routes
Affected wavelengths dropped and re-groomed onto surviving fibres
Playbook analyst guidance by failure mode, not a record of what happened
- FM-01Pre-warn the cable owners of the drift track and re-groom critical wavelengths off the cables on its pathISO 22301
- FM-02Shift traffic from the shared corridor onto non-Red-Sea or terrestrial capacity before more cables are lostISO 22301
- FM-03Re-groom wavelengths and drop low-priority traffic classes first, so premium traffic keeps its pathISO 22301
The crew of container ship Lobivia, who took the 24 Rubymar crew off — Head count, exclusion zones, PPE and the go / no-go for re-entry.
On the record
- Takes all 24 crew off the disabled Rubymar, which is left adrift with its anchor down
All 24 crew evacuated by the container ship Lobivia
Playbook analyst guidance by failure mode, not a record of what happened
The cable repair teams that fixed AAE-1 in July 2024; the operator is not named in the SOE — Restores customer service: failover, workload moves, capacity, backlog drain.
On the record
- AAE-1 repaired in July 2024, about 4-5 months after the cut
repairs were successfully carried out on the AAE-1 cable
Playbook analyst guidance by failure mode, not a record of what happened
- FM-06Recover the damaged cable ends and photograph anchor marks during the repairITIL 4Improvement #6
- FM-04Repair AAE-1 first once permits come, then the remaining two cablesITIL 4
- FM-01Locate each break by OTDR and mark the fault coordinates for the repair vesselITIL 4
- FM-05Mobilise the cable ship with spares and complete the repair as soon as access allowsITIL 4
- FM-02Restore the cut systems in order of capacity carriedITIL 4
- FM-03Return traffic to the repaired cables in steps and check headroom at each stepITIL 4
Cable owners and consortia of AAE-1, EIG and Seacom/TGN-EA — Third party whose product, service or network sits in the failure path.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
- FM-05Pre-position a war-risk-insured repair vessel and spare cable and repeater stock for the Red SeaCorrection of errors #3
- FM-02Commission a route-diversity study and fund at least one Europe-Asia path that avoids Bab-el-MandebCorrection of errors #1
- FM-06Publish fault coordinates, depth and sever-versus-shunt data for each cutCorrection of errors #6
- FM-03Add capacity on a route that does not share the corridor so spare headroom survives a multi-cable lossCorrection of errors #1
- FM-04Ask for naval escort and a de-conflicted route for the repair ship alongside the permitNIMS / ICSImprovement #4
The Yemeni Government, which refused the repair permits, and coastal states — Regulator, investigator or court that establishes cause and obligations after the event.
On the record
- The Yemeni Government refuses permits, so AAE-1 repairs are still pending by 13 May 2024
pending due to the refusal of permits from the Yemeni Government
Playbook analyst guidance by failure mode, not a record of what happened
- FM-06Compare fault coordinates with the vessel's recorded track to confirm or rule out the anchorITIL 4
East African and Gulf carriers and users that depend on the three cables — The tenant or service user: their own redundancy, backups and continuity plan.
On the record
No action by this role appears in the sources.
Playbook analyst guidance by failure mode, not a record of what happened
Failure mode & effects analysis (FMEA)
The Bab-el-Mandeb subsea cable corridor off Yemen and the three systems cut there (Seacom/Tata TGN-Eurasia, AAE-1, EIG): the initiating seabed event, corridor concentration and protection, fault detection and traffic rerouting, repair access under permit refusal and war risk, and fault forensics. There is no official post-mortem and no consortium or regulator root-cause report: the Rubymar dragging anchor is the 'generally accepted' leading hypothesis, resting on temporal and spatial coincidence, and Wikipedia records the cause as 'currently unknown'. The record is telemetry-vendor analysis and press. The ~25% capacity figure is an HGC estimate relayed by Wikipedia and the user count is uncorroborated, so severities are held at 'major degradation' rather than outage, consistent with Cloudflare seeing no material end-user traffic loss in the East African markets it measured. Every corrective action in the dossier is 'Recommended', 'Open' or 'Not started', so no revised score is claimed: all modes are residual risk.
- Caught only after impactD ≥ 8
- 2 of 6
- Actions that cut occurrenceO lowered
- 0
- Actions that cut detectionD lowered
- 0
- Actions that cut severityblast radius unchanged
- 0
FM-04 Repair permits are refused, stalling the repair for monthsRepair permitting in contested Yemeni waters 7·6·6 252 —
- Function
- Authorise repair ships to reach the fault promptly
- Effect
- AAE-1 repairs still pending on 13 May 2024 and completed only in July 2024, about 4-5 months after the cut; Seacom's contribution to Remgro's headline earnings fell from ~R32M to ~R2M, mainly on once-off cable-repair costs
- Cause
- No agreed permitting or safe-passage regime for repair ships; AAE-1 repairs stalled 'due to the refusal of permits from the Yemeni Government'
- Prevention in place
- None recorded
- Detection in place
- Known while the repair was pending
- S 7
- This mode sets how long the capacity loss lasted; months of degraded backbone capacity is a major degradation, scored no higher than the cut itself because end-user traffic was largely carried.
- O 6
- In a contested jurisdiction with no standing regime, a permit obstacle is a foreseeable, weakly guarded condition: 'occasional'.
- D 6
- The obstacle was visible as soon as repair was sought, but nothing could clear it: 'detected at onset, not prevented'.
Corrective action
- Negotiate a standing permitting and safe-passage regime for repair ships in contested Yemeni waters (status: Open) Correction of errors #4
Who acts — playbook
- Authority / investigator Negotiate a standing permitting and safe-passage regime for repair ships in contested Yemeni watersCorrection of errors #4
- First responder Start the permit request on the day of the cut and log the date each refusal arrivesITIL 4
- Incident commander Escalate the refused permit to governments and the UN through the consortium, not through the ship operatorITIL 4
- Vendor / upstream provider Ask for naval escort and a de-conflicted route for the repair ship alongside the permitNIMS / ICSImprovement #4
- Service recovery lead Repair AAE-1 first once permits come, then the remaining two cablesITIL 4
- Customer Plan on months, not weeks, of reduced capacity and re-home critical circuitsISO 22301Lesson #3
On the record at this failure
- Authority / investigator The Yemeni Government refuses permits, so AAE-1 repairs are still pending by 13 May 2024
- Service recovery lead AAE-1 repaired in July 2024, about 4-5 months after the cut
Evidence
- Sequence of events #142024-05 (by 13 May) — AAE-1 repairs still 'pending due to the refusal of permits from the Yemeni Government'.
- Sequence of events #152024-07 — 'In July 2024, repairs were successfully carried out on the AAE-1 cable' — an ~4-5 month restoration versus the days-to-weeks typical in a permissive environment.
- Metric #7Restoration time (AAE-1): ~4-5 months (pending 13 May 2024 -> completed July 2024)
- Contributing factor #4REPAIR-ACCESS GOVERNANCE GAP: AAE-1 repairs stalled specifically due to 'the refusal of permits from the Yemeni Government', with no agreed safe-passage mechanism for repair ships in Houthi-contested waters, turning a routine repair into a ~4-5 month outage (Wikipedia 'AAE-1').
- Reference #6 · news“once-off cable repair costs incurred as a result of cable breaks”
FM-01 A disabled, abandoned vessel drifts with its anchor down across the corridor and, under the leading hypothesis, the dragging anchor shears the cablesSeabed cable route through the Bab-el-Mandeb corridor (external anchor hazard) 7·4·8 224 —
- Function
- Keep armoured cables intact against ship anchors and other seabed activity
- Effect
- Three cable systems severed around 24 February 2024; about a quarter of Europe-Asia-Middle East capacity reported lost
- Cause
- Leading hypothesis, unproven: MV Rubymar, disabled by a Houthi missile on 18 February and abandoned by its 24 crew, drifted more than 70 km while not under command with its anchor down; no salvage or anchor recovery followed and no anchoring-exclusion zone exists in the corridor
- Prevention in place
- Cable armouring; no enforced anchoring-exclusion or cable-protection zone recorded
- Detection in place
- None recorded for the drift; the cuts were registered as loss of optical continuity and in BGP and traffic telemetry
- S 7
- Multi-system loss of international backbone capacity is a major degradation of a major service. Not 8 or 9: rerouting held end-user traffic in the markets Cloudflare measured, and the larger user figures are uncorroborated.
- O 4
- Anchors are the industry's most common cable-fault cause (~70-80% per the ICPC baseline), but this case needed an unusual combination, a war-damaged ship abandoned with its anchor down in the corridor: 'infrequent'. The attribution itself is unproven.
- D 8
- The drift lasted days and nothing recorded acted on it; the event was seen when optical continuity was lost: 'detected after impact by internal monitoring'.
Corrective action
- Designate and enforce an anchoring-exclusion / cable-protection zone off Yemen with AIS monitoring and mariner advisories (status: Open) Correction of errors #2
- Adopt a rapid salvage / anchor-recovery protocol for disabled not-under-command vessels in cable corridors (status: Open) Correction of errors #5
Who acts — playbook
- Authority / investigator Designate an anchoring-exclusion zone off Yemen and push mariner advisories through the IMO and coastal statesCorrection of errors #2
- First responder Watch AIS for any vessel stopped or drifting inside the cable corridor and alert the owners' NOC at onceSRE incident mgmtImprovement #2
- Authority / investigator Tow or salvage a disabled not-under-command ship from a cable corridor before its anchor drags, as the salvage protocol asksCorrection of errors #5
- Operations lead Pre-warn the cable owners of the drift track and re-groom critical wavelengths off the cables on its pathISO 22301
- Service recovery lead Locate each break by OTDR and mark the fault coordinates for the repair vesselITIL 4
On the record at this failure
- Safety officer Takes all 24 crew off the disabled Rubymar, which is left adrift with its anchor down
Evidence
- Sequence of events #22024-02-18 — All 24 crew evacuated by the container ship Lobivia; the disabled, not-under-command vessel is left adrift with its anchor down.
- Sequence of events #32024-02-18 to 02-26 — Unmanned vessel 'moved more than 70 kilometres (43 mi) while not under command', dragging its anchor across the Bab-el-Mandeb seabed cable corridor.
- Contributing factor #3MARITIME PROCEDURE LAPSE: a war-damaged, abandoned, not-under-command vessel was left adrift with its anchor down in a known cable corridor for days (18-26 Feb) with no timely salvage or anchor-recovery — the proximate work-procedure failure that let the anchor drag across the cables (Wikipedia 'MV Rubymar').
- Contributing factor #2NO ENFORCED ANCHORING-EXCLUSION / CABLE-PROTECTION ZONE in the Bab-el-Mandeb corridor — against the ICPC baseline that anchors and fishing cause ~70-80% of all cable faults, the single most expected fault mode was left unmitigated (ICPC industry baseline).
- Metric #9Industry baseline: faults from anchors/fishing: ~70-80% of all cable faults
- Root cause“ATTRIBUTION IS UNPROVEN”
- Reference #2 · press“The cause of the damage is currently unknown”
FM-05 Dispatch is held back by active missile and drone threat, war-risk insurance and naval-security constraintsRepair-ship dispatch and spares under war risk 6·6·6 216 —
- Function
- Mobilise an insured repair vessel with cable and repeater spares into the fault zone
- Effect
- Adds to the months-long restoration in FM-04; repair carried out by an E-Marine cable ship only in July 2024
- Cause
- Active conflict in the repair zone; no pre-positioned war-risk-insured repair capacity recorded
- Prevention in place
- None recorded
- Detection in place
- Known while the repair was pending
- S 6
- It shares the duration effect with FM-04, so it is scored one step lower to avoid counting the same months twice at full weight.
- O 6
- The conflict that disabled the Rubymar was ongoing, so the war-risk condition was present for the whole repair window and weakly guarded: 'occasional'.
- D 6
- Visible from the start, not preventable by any recorded control: 'detected at onset, not prevented'.
Corrective action
- Pre-position war-risk-insured repair vessels and spare cable/repeater stocks for the Red Sea region (status: Open) Correction of errors #3
Who acts — playbook
- Vendor / upstream provider Pre-position a war-risk-insured repair vessel and spare cable and repeater stock for the Red SeaCorrection of errors #3
- First responder Check the repair ship's position, insurance cover and spares inventory against the region quarterlyISO 22301
- Incident commander Decide at once whether to wait for the security situation or send the ship with escortNIMS / ICS
- Authority / investigator Provide naval-security clearance for the repair ship to work in the zoneNIMS / ICS
- Service recovery lead Mobilise the cable ship with spares and complete the repair as soon as access allowsITIL 4
Evidence
- Sequence of events #132024-02 to 07 — Repair-ship dispatch gated by war-risk: active missile/drone threat, war-risk insurance and naval-security constraints delay intervention for months.
- Contributing factor #5ACTIVE CONFLICT / WAR-RISK ENVIRONMENT: ongoing Houthi anti-ship missile and drone threat both created the initiating strike (two missiles, 18 Feb) and blocked timely repair-ship dispatch and salvage (Wikipedia 'MV Rubymar').
- Root cause“the security environment prevented it”
FM-02 Three systems sharing one narrow corridor are severed together by a single eventRoute diversity of Europe-Asia cable systems 7·5·6 210 —
- Function
- Keep nominally independent systems physically independent, so one seabed event cannot cut more than one
- Effect
- Seacom/TGN-Eurasia, AAE-1 and EIG lost at once; impact felt across East African and Gulf markets that lean on them
- Cause
- Route concentration: the systems share the same off-Yemen corridor at the Bab-el-Mandeb chokepoint
- Prevention in place
- Logical diversity across separate cable systems
- Detection in place
- Telemetry at the time of the cuts
- S 7
- This is the route by which one anchor became a three-cable loss, so it carries the same severity as FM-01.
- O 5
- A standing design condition that any seabed event in the corridor exercises; held at 5 so the single event is not counted twice at full weight with FM-01.
- D 6
- Line monitoring and BGP telemetry saw the cuts as they happened, but nothing could prevent a co-located loss: 'detected at onset, not prevented'.
Corrective action
- Commission a route-diversity study and fund at least one non-Bab-el-Mandeb path (status: Recommended) Correction of errors #1
- Route future Europe-Asia systems through geographically diverse paths (analyst recommendation) Improvement #1
Who acts — playbook
- Vendor / upstream provider Commission a route-diversity study and fund at least one Europe-Asia path that avoids Bab-el-MandebCorrection of errors #1
- First responder Map each system's physical route against the others and flag every shared corridor in the carrier risk registerISO 22301
- Incident commander At the first cut, check which other systems share the corridor and treat them as at riskSRE incident mgmt
- Operations lead Shift traffic from the shared corridor onto non-Red-Sea or terrestrial capacity before more cables are lostISO 22301
- Customer Re-home critical circuits to a path outside the corridor and stop relying on logical diversity aloneNIST SP 800-34Lesson #1
- Service recovery lead Restore the cut systems in order of capacity carriedITIL 4
Evidence
- Contributing factor #1ROUTE / CORRIDOR CONCENTRATION (design redundancy gap): three nominally independent systems — Seacom/Tata TGN-Eurasia, AAE-1 and EIG — share the same narrow off-Yemen corridor, so one seabed event severed all at once (Cloudflare Radar Q1-2024).
- Metric #1Subsea cable systems severed: 3 (Seacom/Tata TGN-Eurasia, AAE-1, EIG); HGC reportedly cited 4
- Root cause“The design/redundancy failure is ROUTE CONCENTRATION”
- Reference #4 · press“the Seacom/Tata cable, the Asia Africa Europe-1 (AAE-1), and the Europe India Gateway (EIG)”
FM-06 No instrumented fault forensics are published: no fault coordinates, depths, anchor marks or anchor-track matchFault forensics and attribution 3·8·8 192 —
- Function
- Establish where and how each cable failed, so the cause can be confirmed and acted on
- Effect
- The cause stays 'currently unknown' and rests on coincidence; accountability is hampered and the count of cut systems is reported as three or four
- Cause
- Consortia did not publish fault data; no physical evidence recovered
- Prevention in place
- None recorded
- Detection in place
- Noted by analysts after the event
- S 3
- It does not extend the outage; its effect is on learning and accountability: 'internal impact only'.
- O 8
- Non-publication was the outcome here and the action is 'Not started', so the condition is present whenever a major fault occurs: 'frequent'.
- D 8
- The gap is visible only afterwards, when analysts try to attribute the cut: 'detected after impact'.
Corrective action
- Publish instrumented fault forensics (coordinates, depth, sever-vs-shunt) for major cable faults (status: Not started) Correction of errors #6
Who acts — playbook
- Vendor / upstream provider Publish fault coordinates, depth and sever-versus-shunt data for each cutCorrection of errors #6
- First responder Log the OTDR distance and time for every break at the moment of detection, to support later attributionITIL 4
- Service recovery lead Recover the damaged cable ends and photograph anchor marks during the repairITIL 4Improvement #6
- Authority / investigator Compare fault coordinates with the vessel's recorded track to confirm or rule out the anchorITIL 4
- Incident commander Issue the consortium's findings so the cause stops being only 'generally accepted'ITIL 4
Evidence
- Contributing factor #6NO INSTRUMENTED FAULT FORENSICS PUBLISHED: absence of recovered anchor marks or matched fault-coordinate-versus-anchor-track survey means attribution rests on temporal/spatial coincidence only, hampering accountability and preventing a certified root cause (Wikipedia 'AAE-1' — cause 'currently unknown').
- Sequence of events #16post-incident — No consortium- or regulator-issued root-cause report published; cause officially 'currently unknown' — the record remains telemetry-vendor analysis plus press.
- Metric #1Subsea cable systems severed: 3 (Seacom/Tata TGN-Eurasia, AAE-1, EIG); HGC reportedly cited 4
- Reference #5 · news“It's generally accepted that the Rubymar dropped an anchor”
FM-03 Surviving cables and terrestrial paths lack the headroom to carry the diverted loadFault detection, optical isolation and traffic rerouting 7·3·4 84 —
- Function
- Detect the cut, isolate the severed segments and move traffic to surviving paths before users notice
- Effect
- Did not materialise in the markets measured: Cloudflare saw no material end-user traffic loss in Tanzania, Kenya, Uganda and Mozambique; analysts flag that losing more of the corridor would exhaust the headroom
- Cause
- Finite spare capacity on parallel and terrestrial routes
- Prevention in place
- Parallel Red Sea systems and terrestrial diversity; operators such as HGC rerouting traffic
- Detection in place
- Operator line monitoring/OTDR, plus external BGP, latency and traffic telemetry from Kentik, Cloudflare Radar and NetBlocks
- S 7
- If headroom ran out, the capacity loss would become end-user loss across the same markets: a major degradation.
- O 3
- Headroom held for a three-cable loss, so exhausting it needs a still larger simultaneous loss: between 'remote' and 'infrequent'.
- D 4
- The cuts were visible on capacity and routing telemetry while end-user traffic stayed up, so operators had time to re-groom wavelengths: 'detected before impact with time to act'.
Corrective action
- Fund at least one non-Bab-el-Mandeb path to add headroom that does not share the corridor (status: Recommended) Correction of errors #1
Who acts — playbook
- Vendor / upstream provider Add capacity on a route that does not share the corridor so spare headroom survives a multi-cable lossCorrection of errors #1
- First responder Trend utilisation on surviving cables and terrestrial paths and alert when it passes a set headroom levelSRE incident mgmt
- Operations lead Re-groom wavelengths and drop low-priority traffic classes first, so premium traffic keeps its pathISO 22301
- Incident commander Hold maintenance on the surviving paths during the outageChange management
- Service recovery lead Return traffic to the repaired cables in steps and check headroom at each stepITIL 4
On the record at this failure
- Operations lead HGC moves affected traffic onto surviving cables and terrestrial paths
- Operations lead Operators drop and re-groom wavelengths onto surviving fibres and parallel routes
Evidence
- Sequence of events #72024-02-22 to 02-28 — Cloudflare: 'no loss of traffic was observed across these countries in Cloudflare Radar' (Tanzania, Kenya, Uganda, Mozambique) — fault visible on capacity/routing telemetry while end-user traffic stayed up.
- Sequence of events #82024-02 (late) — Operator HGC reported rerouting affected traffic onto surviving cables and terrestrial paths (protection switching, not suppression).
- Sequence of events #92024-02 (late) — Affected wavelengths dropped and re-groomed onto surviving fibres and parallel/terrestrial routes — optical-layer isolation of the severed segments.
- Metric #3End-user traffic loss observed (Feb 22-28): ~0 (no material loss across affected East-African markets)
- Reference #1 · vendor-status“no loss of traffic was observed across these countries in Cloudflare Radar”
- Technical deep-dive“The residual risk analysts flag is that losing MORE of the corridor simultaneously would exhaust that headroom.”
Scoring rubric and method
Scales adapted from IEC 60812:2018 and AIAG-VDA. RPN = S × O × D. High: S ≥ 9 with O ≥ 4 or D ≥ 7, or RPN ≥ 300. Medium: RPN ≥ 120 or S ≥ 7. Severity overrides the product: 9 × 2 × 9 = 162 would otherwise hide a region-wide outage nothing could catch. Quotes are checked verbatim against this dossier; a revised score needs a published action. RZ analyst assessment, not an operator document.
Severity
| 10 | Hazard to people, or loss of the facility / several regions |
| 9 | Region-wide or provider-wide outage of a foundational service, no workaround |
| 8 | Full outage of a major service for hours |
| 7 | Major degradation of a major service |
| 6 | Partial outage confined to one zone or one service |
| 5 | Customer-visible degradation |
| 4 | Limited customer impact |
| 3 | Internal impact only |
| 2 | Negligible |
| 1 | No effect |
Occurrence
| 10 | Near certain: the cause is present in normal operation |
| 8 | Frequent: routine work exercises the cause |
| 6 | Occasional: a foreseeable slip or condition, weakly guarded |
| 4 | Infrequent: needs an unusual combination |
| 2 | Remote: guarded by design |
| 1 | Eliminated by design |
Detection
| 10 | No control could detect it |
| 9 | Detected only through customer impact |
| 8 | Detected after impact by internal monitoring |
| 6 | Detected at onset, not prevented |
| 4 | Detected before impact with time to act |
| 2 | Automated interlock almost certainly stops it |
| 1 | Certain to be stopped |
Root cause and contributing factors
Full root-cause narrative
Contributing factors by category
- ROUTE / CORRIDOR CONCENTRATION (design redundancy gap): three nominally independent systems — Seacom/Tata TGN-Eurasia, AAE-1 and EIG — share the same narrow off-Yemen corridor, so one seabed event severed all at once (Cloudflare Radar Q1-2024).
- NO ENFORCED ANCHORING-EXCLUSION / CABLE-PROTECTION ZONE in the Bab-el-Mandeb corridor — against the ICPC baseline that anchors and fishing cause ~70-80% of all cable faults, the single most expected fault mode was left unmitigated (ICPC industry baseline).
- MARITIME PROCEDURE LAPSE: a war-damaged, abandoned, not-under-command vessel was left adrift with its anchor down in a known cable corridor for days (18-26 Feb) with no timely salvage or anchor-recovery — the proximate work-procedure failure that let the anchor drag across the cables (Wikipedia 'MV Rubymar').
- REPAIR-ACCESS GOVERNANCE GAP: AAE-1 repairs stalled specifically due to 'the refusal of permits from the Yemeni Government', with no agreed safe-passage mechanism for repair ships in Houthi-contested waters, turning a routine repair into a ~4-5 month outage (Wikipedia 'AAE-1').
- ACTIVE CONFLICT / WAR-RISK ENVIRONMENT: ongoing Houthi anti-ship missile and drone threat both created the initiating strike (two missiles, 18 Feb) and blocked timely repair-ship dispatch and salvage (Wikipedia 'MV Rubymar').
- NO INSTRUMENTED FAULT FORENSICS PUBLISHED: absence of recovered anchor marks or matched fault-coordinate-versus-anchor-track survey means attribution rests on temporal/spatial coincidence only, hampering accountability and preventing a certified root cause (Wikipedia 'AAE-1' — cause 'currently unknown').
Analysis
Nature of the incident — mechanical severance, not a fire
This is a subsea-cable incident with no data-centre, no combustion, no fixed-facility evacuation and no electrical de-energisation in the fire sense. The fire-report schema is therefore mapped, not applied literally: 'ignition source/equipment' becomes the dragging anchor and chain of MV Rubymar; 'detection' becomes network telemetry (BGP, latency, OTDR); 'suppression' becomes traffic rerouting; 'evacuation' refers to the vessel crew; 'emergency services' becomes repair-ship dispatch. Non-applicable fire categories are flagged, not invented.
Attribution: unproven, coincidence-based
No operator or investigator published a positive, instrumented root cause. Wikipedia calls the Rubymar anchor 'One hypothesis' and states the cause is 'currently unknown'. The case rests entirely on temporal and spatial coincidence: the vessel drifted >70 km with its anchor down between 18 and 26 February, and Cloudflare dated the cuts to 24 February in the same corridor. No recovered anchor marks and no matched fault-coordinate-versus-anchor-track survey exist. The dossier states this plainly rather than asserting a proven cause.
The real systemic lesson — corridor concentration
Three nominally independent systems (Seacom/Tata TGN-Eurasia, AAE-1, EIG) share the narrow, shallow, contested Bab-el-Mandeb corridor, so a single seabed event severed all at once. There is no enforced anchoring-exclusion zone, despite the ICPC baseline that ~70-80% of cable faults come from human activity such as anchoring and fishing. The failure is design redundancy (route diversity), not cable maintenance — the cables were in normal service and failed to external impact.
Why recovery took months — geopolitics, not engineering
Restoration was gated by access, not splice time. Wikipedia records AAE-1 repairs 'pending due to the refusal of permits from the Yemeni Government', compounded by active missile/drone threat, war-risk insurance and naval-security constraints. Repairs were completed in July 2024 — roughly 4-5 months, versus days-to-weeks in a permissive environment. The absence of a standing safe-passage/permitting regime for repair ships is the governance root of the prolonged outage.
Resilience that worked — capacity headroom vs end-user impact
Despite ~25% of Europe-Asia-Middle East capacity being lost, Cloudflare states 'no loss of traffic was observed across these countries in Cloudflare Radar' (Tanzania, Kenya, Uganda, Mozambique) during 22-28 February. Rerouting onto surviving fibres, parallel systems and terrestrial paths absorbed the load. The mitigation largely worked; the residual risk analysts flag is that losing more of the same corridor simultaneously would exhaust that headroom.
Technical deep-dive
Corrective actions and lessons
Correction of errors
| Action | Owner | Status |
|---|---|---|
| Commission a geographic route-diversity study for Europe-Asia traffic and fund at least one non-Bab-el-Mandeb path. | Cable consortia / carriers (AAE-1, EIG, Seacom, Tata) | Recommended |
| Designate and enforce an anchoring-exclusion / cable-protection zone off Yemen with AIS monitoring and mariner advisories. | IMO / coastal states / ICPC | Open |
| Pre-position war-risk-insured repair vessels and spare cable/repeater stocks for the Red Sea region. | Cable operators / regional maintenance authority | Open |
| Negotiate a standing permitting and safe-passage regime for repair ships in contested Yemeni waters. | Governments (Aden) / UN / operators | Open |
| Adopt a rapid salvage / anchor-recovery protocol for disabled not-under-command vessels in cable corridors. | Coastal states / salvors / IMO | Open |
| Publish instrumented fault forensics (coordinates, depth, sever-vs-shunt) for major cable faults. | Cable consortia | Not started |
Lessons learnt
- A single physical hazard at a shared chokepoint can take out multiple independent backbones at once — logical diversity means little when cables are geographically co-located.
- Surface-conflict risk translates directly into subsea-infrastructure risk: an abandoned, adrift vessel with a dropped anchor is a cable-cut mechanism, not just a shipping incident.
- Restoration time, not the cut itself, drove the impact: security-constrained repair access stretched a fault into a ~5-month capacity loss.
- Impact reporting for subsea incidents is systematically weak — the headline ~25%-traffic and 'tens of millions' figures could not be tied to any named source in reachable references, so severity is easily over- or under-stated.
- Financial disclosure is opaque: only a downstream shareholder (Remgro) surfaced a hard number, and even then only an earnings delta (~R30M), never the actual repair bill.
- 'Generally accepted' is not 'verified' — absent a consortium forensic report, the exact failure geometry and the precise status of TGN-EA (distinct cable vs. shared with Seacom) remain open.
Improvements
- DesignBreak the Bab-el-Mandeb single-corridor dependency — route future Europe-Asia systems through geographically diverse paths (alternative Red Sea landings, overland/terrestrial bypasses, or non-Red-Sea routes) so no single seabed event can sever three independent systems at once (Cloudflare Radar Q1-2024).
- SafetyEstablish and enforce anchoring-exclusion / cable-protection zones over the off-Yemen corridor with AIS-based monitoring and mariner advisories, targeting the ICPC-identified dominant fault mode (anchors/fishing ~70-80% of faults) (ICPC industry baseline).
- MaintenancePre-position war-risk-insured cable-repair capacity and standing spare-cable/repeater stocks for the Red Sea region, plus routine OTDR/line-monitoring baselining, so restoration is not gated on ad-hoc mobilisation into a contested zone (Wikipedia 'AAE-1').
- ProcessNegotiate a standing permitting and safe-passage regime for cable-repair vessels in contested Yemeni waters that de-conflicts jurisdiction and secures naval escort, to prevent the multi-month permit-refusal delays seen here (Wikipedia 'AAE-1').
- ProcessInstitute rapid maritime salvage / anchor-recovery protocols for disabled, not-under-command vessels adrift in known cable corridors, so an abandoned ship's dragging anchor is arrested before it can traverse 70+ km of seabed (Wikipedia 'MV Rubymar').
- MaintenanceRequire operators to publish instrumented fault forensics (fault coordinates, depth, sever-vs-shunt) and, where safe, recover physical evidence, so future attribution rests on data rather than temporal coincidence (Wikipedia 'AAE-1').
References and provenance
- vendor-status Cloudflare Radar — Q1 2024 Internet Disruption Summary“no loss of traffic was observed across these countries in Cloudflare Radar”https://blog.cloudflare.com/q1-2024-internet-disruption-summary/
- press Wikipedia — AAE-1 (cause unconfirmed)“The cause of the damage is currently unknown, and due to the sensitivity of the location”https://en.wikipedia.org/wiki/AAE-1
- press Wikipedia — MV Rubymar (attack)“on 18 February 2024, Houthi forces launched two anti-ship missiles at the ship, one of which struck it”https://en.wikipedia.org/wiki/MV_Rubymar
- press Cloudflare — East African Internet connectivity again impacted by submarine cable cuts“the Seacom/Tata cable, the Asia Africa Europe-1 (AAE-1), and the Europe India Gateway (EIG) ... these cables remain unrepaired”https://blog.cloudflare.com/east-african-internet-connectivity-again-impacted-by-submarine-cable-cuts
- news Red Sea cable break eats away at Seacom“It's generally accepted that the Rubymar dropped an anchor when fired upon and, as a result, it damaged cables in proximity”https://techcentral.co.za/red-sea-cable-break-eats-away-at-seacom/261286/
- news Red Sea cable break eats away at Seacom (Remgro earnings disclosure)“The decrease in headline earnings relates mainly to once-off cable repair costs incurred as a result of cable breaks”https://techcentral.co.za/red-sea-cable-break-eats-away-at-seacom/261286/
- other What Caused the Red Sea Submarine Cable Cuts? (Kentik / Doug Madory)“Disruptions in East Africa, often involving the loss of Tata transit, occurred at 09:46 UTC ... that is when Seacom suffered its failure”https://www.kentik.com/blog/what-caused-the-red-sea-submarine-cable-cuts/
- news Undersea cables cut in Red Sea, disrupting internet — Houthis suspected“Undersea cables cut in Red Sea, disrupting internet ... Houthis suspected”https://www.timesofisrael.com/undersea-cables-cut-in-red-sea-disrupting-internet-in-parts-of-region-houthis-suspected/
Quotes are short, attributed, and for provenance only; the analysis is original. Last verified 2026-08-01.